Inspection Detail
Inspection: 309847127 - Synthron, Inc.
Inspection Information - Office: Nc Department Of Labor - Charlotte
Site Address:
Synthron, Inc.
305 Amherst Road
Morganton, NC 28655
Mailing Address:
420 C West Fleming Drive, Morganton, NC 28655
Union Status: NonUnion
SIC:2869
NAICS: 325998/All Other Miscellaneous Chemical Product and Preparation Manufacturing
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 07/24/2006
Planning Guide: Safety-Manufacturing
Emphasis: N:Psmpqv
Case Closed: 04/06/2010
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 102095908 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 21 | 8 | 7 | 36 | ||
Current Violations | 21 | 8 | 7 | 36 | ||
Initial Penalty | $29,400 | $315,000 | $0 | $0 | $0 | $344,400 |
Current Penalty | $21,525 | $168,000 | $0 | $0 | $0 | $189,525 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Willful | 19100119 C01 | 07/24/2006 | 08/01/2006 | $21,000 | $21,000 | $0 | 09/07/2006 | F - Formal Settlement | |
2. | 01002 | Willful | 19100119 D | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
3. | 01003 | Willful | 19100119 E01 | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
4. | 01004 | Willful | 19100119 F01 | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
5. | 01005 | Willful | 19100119 G01 I | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
6. | 01006A | Willful | 19100119 J02 | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
7. | 01006B | Willful | 19100119 J03 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
8. | 01007 | Willful | 19100119 L01 | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
9. | 01008 | Willful | 19100307 B | 07/24/2006 | 08/01/2006 | $21,000 | $42,000 | $0 | 09/07/2006 | F - Formal Settlement | |
10. | 02001 | Serious | 19100038 F01 | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
11. | 02002 | Serious | 19100106 H03 IIA | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
12. | 02003 | Serious | 19100106 H04 IVA | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
13. | 02004 | Serious | 19100106 H04 IIIA | 07/24/2006 | 08/01/2006 | $525 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
14. | 02005 | Serious | 19100120 Q01 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
15. | 02006 | Serious | 19100120 Q06 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
16. | 02007 | Serious | 19100120 Q09 I | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
17. | 02008 | Serious | 19100134 F01 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
18. | 02009 | Serious | 19100134 H03 IB | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
19. | 02010 | Serious | 19100134 K03 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
20. | 02011 | Serious | 19100134 M02 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
21. | 02012A | Serious | 19100146 C04 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
22. | 02012B | Serious | 19100146 G01 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
23. | 02013A | Serious | 19100147 C01 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
24. | 02013B | Serious | 19100147 F02 I | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
25. | 02014 | Serious | 19100165 B05 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
26. | 02015 | Serious | 19100178 C02 IV | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
27. | 02016 | Serious | 19101001 J02 I | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
28. | 02017 | Serious | 19101048 D02 II | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
29. | 02018 | Serious | 19101048 M05 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
30. | 02019 | Serious | 19101200 E01 | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
31. | 02020 | Serious | 19101200 F05 | 07/24/2006 | 08/01/2006 | $1,050 | $1,050 | $0 | 09/07/2006 | F - Formal Settlement | |
32. | 02021A | Serious | 19101200 H01 | 07/24/2006 | 08/01/2006 | $1,050 | $2,100 | $0 | 09/07/2006 | F - Formal Settlement | |
33. | 02021B | Serious | 19101200 H03 III | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
34. | 03001 | Other | 19100132 F01 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
35. | 03002 | Other | 19100134 E01 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
36. | 03003 | Other | 19100157 E02 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
37. | 03004 | Other | 19100178 L01 II | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
38. | 03005 | Other | 19100178 L05 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
39. | 03006 | Other | 19100178 L06 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement | |
40. | 03007 | Other | 19100178 Q07 | 07/24/2006 | 08/01/2006 | $0 | $0 | $0 | 09/07/2006 | F - Formal Settlement |
Investigation Summary
On January 31, 2006, a runaway reaction occurred at Synthron, Inc., while employees were making Modarez MFP-BH. The polymerization reaction included toluene, cyclohexane, n-butyl acrylate, and benzoyl peroxide. According to the employer's records, there were 2,689 pounds of the solvent blend and 1,923 pounds of N-Butyl Acrylate in a Pfaudler reactor (M-1). Two 55-gallon drums and one 330-gallon IBC tote were positioned in front of reactor M-1. The containers held a solvent blend of toluene, cyclohexane, and benzoyl peroxide. At the time of the incident, the contents of one of the drums and a portion of a second drum had been transferred to the M-1 reactor. Employee #1 walked away from the reactor, intending to turn a valve on the M-5 reactor to begin a nitrogen purge and move the contents of M-5 to M-1. While walking down a stair to perform this task, Employee #1 heard a loud, high-pitched sound. He immediately went back up and observed the Teflon 18 in. envelope gasket from M-1 hanging down from the manway and vapors coming through the opening. Other employees began to hear the sound. After Employee #1 observed the vapors being emitted, he walked outside and met other employees outside the production door, on the Northwest side of the building. Employee #2 was operating a forklift inside the drumming area when he heard the sound. He left the area and met with Employee #3 and Employee #4. They walked up to the Northwest side of the building. Employee #5 instructed Employee #3 to go get the Plant Manager. Employee #5 then donned a full-face respirator and entered the building to turn on the chill water to the reactor. After a few seconds, Employee #5 returned after failing to obtain a good seal on the respirator and smelling vapors. Employee #1 then donned the respirator and went inside the building. Employee #3 and Employee #6 walked up and joined the other employees outside the production door. When Employee #1 exited the building, an explosion occurred. Twelve employees and two bystanders sustained various injuries. Five of the employees were hospitalized with various injuries, and one died later of burns.
Keywords: BURN, LEAK, FRACTURE, VAPOR, EXPLOSION, CHEMICAL REACTION, CHEMICAL BURN, CHEMICAL VAPOR, CHEMICAL, RESPIRATOR
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 309847127 | Fatality | Burn/Scald(Heat) | Not specified mechanics and repairers | ||
2 | 309847127 | Hospitalized injury | Bruise/Contus/Abras | Occupation not reported | ||
3 | 309847127 | Non Hospitalized injury | Other | Occupation not reported | ||
4 | 309847127 | Hospitalized injury | Burn/Scald(Heat) | Not specified mechanics and repairers | ||
5 | 309847127 | Hospitalized injury | Burn/Scald(Heat) | Management related occupations, n.e.c. | ||
6 | 309847127 | Hospitalized injury | Fracture | Occupation not reported | ||
7 | 309847127 | Non Hospitalized injury | Other | Occupation not reported | ||
8 | 309847127 | Non Hospitalized injury | Bruise/Contus/Abras | Occupation not reported | ||
9 | 309847127 | Non Hospitalized injury | Strain/Sprain | Occupation not reported | ||
10 | 309847127 | Non Hospitalized injury | Other | Occupation not reported | ||
11 | 309847127 | Non Hospitalized injury | Other | Managers, marketing, advertising, & public rela. | ||
12 | 309847127 | Non Hospitalized injury | Strain/Sprain | Occupation not reported |