Case Study 5: Sour Water Pipeline Repairs


Incorrect.  In this scenario, it would.

More than one authorized employee was involved in this particular servicing and maintenance activity; therefore, the energy control procedures must include the group lockout/tagout provisions.

For more information: Refer to 29 CFR 1910.147(f)(3) of the Lockout/Tagout standard. Also refer to The Control of Hazardous Energy – Enforcement Policy and Inspection Procedures.