There are two sources of electrical power used during
building and repair of a vessel -- shore side and vessel generated. (See diagram).
The potential for electrical shock hazards is greater
in shipbuilding and repair than in other industries, because workers stand on metal
decks and often work in a wet environment. Work on or around
energized electrical equipment can expose workers to electrocution,
burns, or electrical shock. Before work is performed, energized equipment
must be guarded, deenergized, or appropriate PPE used to prevent worker
exposure. [29 CFR 1915.181, 29 CFR 1915.157(c)]
Note: 1910 Subpart S: Electrical and the
National Electric Code (NFPA 70) do not apply to the vessel's electrical
system.
Use of portable electrical tools and lighting can
also be found in the following modules:
For shipbuilding:
For ship repair:
Note: Confined space entry is one of the leading
hazards associated with barge cleaning. Review the Ship Repair: Confined or Enclosed Spaces and Other Dangerous Atmospheres chapter for information on how to protect workers from this hazard.
Electrical Circuits and Distribution Boards |

Figure 1: Improper practice - Faulty breaker box presents shock hazard.
 Figure 2: Portable distribution panel used to supply temporary electrical power.

Figure 3: Circuit breakers in panel box can be used to deenergize circuits (and appropriately tagged) before working on the circuit.
The Electrical Circuit and Distribution Board
Standard [29 CFR 1915.181] applies to the vessel's permanently installed
electrical circuits and distribution systems. Temporarily installed
electrical systems (such as extension cords, portable service panel,
"spider box") used for repairing of the vessel is
covered in Tools and Related Equipment [29 CFR 1915.132] and General Working Conditions
[29 CFR 1915.92 and
29 CFR 1915.93(b)].
Potential Hazards:
-
Worker
electrical shock, burns, or electrocution due to contact with or near to energized
electrical equipment.
-
Falls from
elevations.
Requirements and Example Solutions:
-
Before work is performed on circuits, except
those
being tested or adjusted, circuits must be deenergized and checked at
the point where work will be performed to ensure the circuits are
actually deenergized. [29 CFR 1915.181(b)]
-
When testing or adjusting energized circuits, a
rubber or other suitable insulated deck mat must be used. [29 CFR 1915.181(b)]
-
Deenergizing the circuit must be appropriately completed by
opening the circuit breaker, opening the switch, or removing the fuse.
[29 CFR 1915.181(c)]
-
The circuit breaker, switch, or fuse
location must be tagged to indicate work is occurring on
the circuit. Such tags must not be removed nor the circuit energized
until the work has
been completed. [29 CFR 1915.181(c)]
-
When work is performed immediately adjacent to exposed
energized parts, these parts must be covered (for example, insulated) or other equally safe means
provided. [29 CFR 1915.181(d)]
Note: Control of Hazardous Energy Sources (Lockout/Tagout)
standard [29 CFR 1910.147]
does not apply to Ship Repair.
- Insulating materials (such as mats and gloves) should be periodically
tested or inspected.
- All electrical tools or equipment should undergo a visual inspection
before use.
- All portable electric hand tools and temporary lighting systems
should utilize Ground Fault Circuit Interrupters (GFCI).
- Electrical tools and equipment should correspond with the
requirements of the job.
- Electrical equipment and tools should be used with proper circuit
protection for the voltage and amperage used.
- Only qualified electricians should attempt repair of electrical
tools and equipment in use.
- A Ground Assurance Program should be in place for all electrical
tools and equipment used including:
- Records of tools inspected and repaired.
- Records of electrical boxes inspected and repaired.
- Records of electrical extension cords inspected and repaired.
- Recall of records of the above.
- The requirements of the Ground Assurance Program should be performed
on a regular basis.