Regulations (Standards - 29 CFR) - Table of Contents
• Part Number: 1926
• Part Title: Safety and Health Regulations for Construction
• Subpart: AA
• Subpart Title: Confined Spaces in Construction
• Standard Number: 1926.1205
• Title: Permitting process.
• GPO Source: e-CFR

1926.1205(a)

Before entry is authorized, each entry employer must document the completion of measures required by § 1926.1204(c) by preparing an entry permit.

1926.1205(b)

Before entry begins, the entry supervisor identified on the permit must sign the entry permit to authorize entry.

1926.1205(c)

The completed permit must be made available at the time of entry to all authorized entrants or their authorized representatives, by posting it at the entry portal or by any other equally effective means, so that the entrants can confirm that pre-entry preparations have been completed.

1926.1205(d)

The duration of the permit may not exceed the time required to complete the assigned task or job identified on the permit in accordance with § 1926.1206(b).

1926.1205(e)

The entry supervisor must terminate entry and take the following action when any of the following apply:

1926.1205(e)(1)

Cancel the entry permit when the entry operations covered by the entry permit have been completed; or

1926.1205(e)(2)

Suspend or cancel the entry permit and fully reassess the space before allowing reentry when a condition that is not allowed under the entry permit arises in or near the permit space and that condition is temporary in nature and does not change the configuration of the space or create any new hazards within it; and

1926.1205(e)(3)

Cancel the entry permit when a condition that is not allowed under the entry permit arises in or near the permit space and that condition is not covered by paragraph (e)(2) of this section.

1926.1205(f)

The entry employer must retain each canceled entry permit for at least 1 year to facilitate the review of the permit-required confined space program required by § 1926.1204(n). Any problems encountered during an entry operation must be noted on the pertinent permit so that appropriate revisions to the permit space program can be made.
[80 FR 25524, May 4, 2015]

Next Standard (1926.1206)

Regulations (Standards - 29 CFR) - Table of Contents

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close