Powered by GoogleTranslate

Occupational Safety and Health Administration OSHA

Inspection Detail

Inspection: 312635857 - U.S. Steel Corporation

Inspection Information - Office: Pittsburgh

Nr: 312635857Report ID: 0317500Open Date: 07/14/2010

U.S. Steel Corporation
400 State Street
Clairton, PA 15025
Union Status: Union
SIC: 3312/Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
NAICS: 331111/Iron and Steel Mills

Inspection Type:Accident
Scope:Complete Advanced Notice:N
Ownership:Private
Safety/Health:Health Close Conference:01/13/2011
Close Case:12/13/2012

Related Activity:TypeIDSafetyHealth
 Accident100541713    

Violation Summary
Serious Willful Repeat Other Unclass Total
Initial Violations 8 8
Current Violations 3 1 4
Initial Penalty $52,500 $0 $0 $0 $0 $52,500
Current Penalty $17,500 $0 $0 $500 $0 $18,000
FTA Amount $0 $0 $0 $0 $0 $0

Violation Items
# ID Type Standard Issuance Abate Curr$ Init$ Fta$ Contest LastEvent
Deleted 1. 01001 Serious 19100119 D 01/13/2011 02/15/2011 $0 $7,000 $0 02/01/2011 F - Formal Settlement
Deleted 2. 01002 Serious 19100119 E01 01/13/2011 02/15/2011 $0 $7,000 $0 02/01/2011 F - Formal Settlement
Deleted 3. 01003 Serious 19100119 F04 01/13/2011 01/31/2011 $0 $7,000 $0 02/01/2011 F - Formal Settlement
  4. 01004 Serious 19100119 J04 III 01/13/2011 01/13/2013 $7,000 $7,000 $0 02/01/2011 F - Formal Settlement
Deleted 5. 01005 Serious 19100120 Q01 01/13/2011 02/15/2011 $0 $7,000 $0 02/01/2011 F - Formal Settlement
  6. 01006 Other 19100134 D01 III 01/13/2011 01/19/2011 $500 $7,000 $0 02/01/2011 F - Formal Settlement
  7. 01007 Serious 19100138 A 01/13/2011 01/19/2011 $3,500 $3,500 $0 02/01/2011 F - Formal Settlement
  8. 01008 Serious 19100307 C 01/13/2011 01/31/2011 $7,000 $7,000 $0 02/01/2011 F - Formal Settlement

Accident Investigation Summary
Summary Nr: 200542017Event: 07/14/2010Two Employees Are Burned In Explosion At Coke Oven
At approximately 9:30 a.m. on July 14, 2010, Employees #1 and #2 were installing a big hole and little hole blind flange between a gate valve and a 30-in. pipe containing coke oven gas. The work was part of an attempt to isolate the Preheater from the underfire system for cleaning. When the contractors removed the spacer ring connecting the two flanges, coke oven gas was released. Shortly thereafter, portable and fixed alarms began to sound, warning of potential hazards. Subsequently, an ignition source was found and an explosion occurred. Following the explosion, US Steel shutoff the supply of gas by closing and placing a water seal on top of the Pad valve located outside the battery. A nitrogen truck was brought in and used to purge the under fire system. As a result of the explosion, Employees #1 and #2 sustained first, second, and third degree burns as well as other unspecified serious injuries. The employees were hospitalized and treated for burns. Coworkers were then able to enter the battery wearing supplied air respirators and tighten the bolts securing the blind flange. This was a feasible option prior to the explosion instead of the procedure attempted that morning. The failure to follow recognized energy control requirements contributed to the incident.
Keywords: burn, flammable liquid, coke oven, fire, gas, explosion
Inspection Degree Nature Occupation
1 312635857 Hospitalized injury Burn/Scald(Heat) Occupation not reported

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close