Inspection Detail

Inspection: 304313984 - B & B Utility Contractors, Inc.

Inspection Information - Office: Jackson Area Office

 

Inspection Nr: 304313984
Report ID: 0419400
Date Opened: 04/25/2002

Site Address:
B & B Utility Contractors, Inc.
King Road, Sect. 32, T8n, R3e, Jefferson Co., Ms
Union Church, MS 39668

Mailing Address:
P.O. Box 5868, Brandon, MS 39047

Union Status: NonUnion

SIC:1623

NAICS: 0 


Inspection Type: Accident

Scope: Complete

Advanced Notice: Y

Ownership: Private

Safety/Health: Safety

Close Conference: 10/16/2002

Planning Guide: Safety-Construction

Emphasis: S:Construction, S:Construction Fatalities

Case Closed: 11/22/2002


Related Activity
Type Activity Nr Safety Health
Accident 101362820
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 1 1
Current Violations 1 1
Initial Penalty $4,900 $0 $0 $0 $0 $4,900
Current Penalty $3,000 $0 $0 $0 $0 $3,000
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19260950 C01 10/16/2002 10/21/2002 $3,000 $4,900 $0 I - Informal Settlement  

Investigation Summary

Investigation Nr: 201361854
Event: 04/17/2002
ELECTRIC SHOCK - DIRECT CONTACT WITH OVERHEAD LINE

An apprentice power line worker was in an aerial lift, working on a new overhead power line being installed along a rural gravel road. He was approaching an existing single-phase 7200-volt overhead power line with a grounded AWG #2 triplex service drop cable in the boom's jib. He was going to connect a service drop to a transformer. The young employee had earlier moved the transformer from an old 12.2-meter-tall pole to a new pole that was 13.7 meters tall. The employee was not wearing his rubber insulating gloves (which were still in the glove bag hanging from the tool board in the bucket), nor had he placed the rubber insulating line hose (which was also in the bucket with him) on the energized phase conductor. No one was observing him while he was working. The employee maneuvered the aerial lift bucket between the phase and neutral conductors on the existing power line, with the bucket at a 45-degree angle to the boom. The end of the triplex cable was inside the bucket with the employee. The existing line was located parallel to and closer to the gravel road than the new line being installed. The employee apparently contacted the phase conductor and was electrocuted. His supervisor found him slumped down in his bucket with the existing phase conductor running diagonally across the top of the bucket's liner and behind the dead employee.

Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, ELEC UTILITY WORK, AERIAL LIFT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 304313984 Fatality Electric Shock Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.