Inspection Detail
Inspection: 303396345 - Pse&G
Inspection Information - Office: Marlton Area Office
Site Address:
Pse&G
Red Bank Ave.
Woodbury, NJ 08096
Mailing Address:
300 New Albany Rd, Moorestown, NJ 08057
Union Status: Union
SIC:4911
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: Y
Ownership: Private
Safety/Health: Health
Close Conference: 08/23/2002
Emphasis:
Case Closed: 11/01/2002
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 101771798 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 5 | 1 | 6 | |||
Current Violations | 2 | 1 | 3 | |||
Initial Penalty | $18,500 | $0 | $0 | $0 | $0 | $18,500 |
Current Penalty | $5,000 | $0 | $0 | $0 | $0 | $5,000 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19100269 D02 VIIB | 10/03/2002 | 10/08/2002 | $0 | $5,000 | $0 | I - Informal Settlement | Citation has been deleted. | |
2. | 01002 | Serious | 19100269 D06 VII | 10/03/2002 | 10/08/2002 | $0 | $5,000 | $0 | I - Informal Settlement | Citation has been deleted. | |
3. | 01003A | Serious | 19100269 W07 | 10/03/2002 | 10/08/2002 | $0 | $3,500 | $0 | I - Informal Settlement | Citation has been deleted. | |
4. | 01003B | Serious | 19100269 M03 V | 10/03/2002 | 10/08/2002 | $0 | $0 | $0 | I - Informal Settlement | Citation has been deleted. | |
5. | 01004 | Serious | 19100269 M03 V | 10/03/2002 | 10/08/2002 | $2,500 | $2,500 | $0 | I - Informal Settlement | ||
6. | 01005 | Serious | 19100269 U05 II | 10/03/2002 | 10/08/2002 | $2,500 | $2,500 | $0 | I - Informal Settlement | ||
7. | 02001 | Other | 19100269 A02 IIA | 10/03/2002 | 11/05/2002 | $0 | $0 | $0 | I - Informal Settlement |
Investigation Summary
Four electric utility employees were verifying ratio changes in transformers at a substation. The lead employee entered the compartment of an air circuit breaker to place a test lead on a deenergized 4160-volt bus. He contacted an energized 4160-volt busbar instead and caused an electrical fault. The ensuing electric arc severely burned the four employees. They were hospitalized for their injuries.
Keywords: BURN, ELECTRIC ARC, ELECTRICAL, POWER LINE WORKER, TEST EQUIPMENT, E PTD, SUBSTATION, CIRCUIT BREAKER, ELEC UTILITY WORK, ELECTRICAL FAULT
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 303396345 | Hospitalized injury | Burn/Scald(Heat) | Electrical power installers and repairers | ||
2 | 303396345 | Hospitalized injury | Burn/Scald(Heat) | Electrical power installers and repairers | ||
3 | 303396345 | Hospitalized injury | Burn/Scald(Heat) | Electrical power installers and repairers | ||
4 | 303396345 | Hospitalized injury | Burn/Scald(Heat) | Electrical power installers and repairers |