Powered by GoogleTranslate

Inspection Detail

Inspection: 123173510 - Ducci Electrical Contractors, Inc.

Inspection Information - Office: Bridgeport Area Office

 

Inspection Nr: 123173510
Report ID: 0111500
Date Opened: 10/07/1993

Site Address:
Ducci Electrical Contractors, Inc.
842 Howard Avenue
New Haven, CT 06510

Mailing Address:
427 Goshen Road, Torrington, CT 06790

Union Status: Union

SIC:1731

NAICS: 0 


Inspection Type: Referral

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Health

Close Conference: 10/07/1993

Emphasis:

Case Closed: 07/18/1994


Related Activity
Type Activity Nr Safety Health
Referral 901485383 Yes
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 6 6
Current Violations 5 5
Initial Penalty $24,500 $0 $0 $0 $0 $24,500
Current Penalty $11,000 $0 $0 $0 $0 $11,000
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citation Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 5A0001 11/12/1993 01/03/1994 $4,500 $4,500 $0 11/29/1993 F - Formal Settlement Citation has been deleted.
2. 01002 Serious 19260021 B06 I 11/12/1993 01/03/1994 $1,000 $4,500 $0 11/29/1993 F - Formal Settlement  
3. 01003 Serious 19260028 A 11/12/1993 11/18/1994 $4,250 $4,500 $0 11/29/1993 F - Formal Settlement  
4. 01004A Serious 19260154 A02 11/12/1993 11/18/1993 $4,500 $4,500 $0 11/29/1993 F - Formal Settlement Citation has been deleted.
5. 01004B Serious 19260956 A03 I 11/12/1993 11/18/1993 $0 $0 $0 11/29/1993 F - Formal Settlement Citation has been deleted.
6. 01004C Serious 19260956 B02 11/12/1993 11/18/1994 $1,500 $0 $0 11/29/1993 F - Formal Settlement  
7. 01005 Serious 19260956 A01 11/12/1993 11/18/1993 $2,000 $2,000 $0 11/29/1993 F - Formal Settlement  
8. 01006 Serious 19260956 B01 11/12/1993 11/18/1994 $2,250 $4,500 $0 11/29/1993 F - Formal Settlement  

Investigation Summary

Investigation Nr: 170034870
Event: 10/07/1993
BURN - PROPANE GAS EXPLOSION IN MANHOLE

Two power line workers were in a manhole, making a T-splice on an underground power line cable. They were using a 9-kilogram tank of propane to heat the lead around the splice. The employees were 3 meters below ground level with a wooden ladder for egress but no lifelines. The propane tank exploded, and flames engulfed their upper extremities, including their head, face, arms, and hands. They were hospitalized for their injuries. It appeared that the propane tank might have been leaking around the neck, causing a flammable atmosphere.

Keywords: BURN, LEAK, CONFINED SPACE, FLAMMABLE VAPORS, POWER LINE WORKER, TORCH, UNDRGRD INSTALLATION, ELEC UTILITY WORK, PROPANE

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 123173510 Hospitalized injury Burn/Scald(Heat) Electrical power installers and repairers
2 123173510 Hospitalized injury Burn/Scald(Heat) Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.