Inspection Detail
Case Status: CLOSED |
Inspection: 1229944.015 - Trueblue Inc.
|
Inspection Information - Office: Boston North | ||||
Nr: 1229944.015 | Report ID: 0134000 | Open Date: 05/04/2017 | ||
Trueblue Inc. | ||||
400 Charter Way Billerica, MA 01822 | Union Status: NonUnion | |||
SIC: | ||||
NAICS: 561320/Temporary Help Services | ||||
Mailing: 517 Central Ave, Dover, NH 03820 | ||||
Inspection Type: | Fat/Cat | |||
Scope: | Complete | Advanced Notice: | N | |
Ownership: | Private | |||
Safety/Health: | Safety | Close Conference: | 05/04/2017 | |
Close Case: | 02/23/2018 | |||
Related Activity: | Type | ID | Safety | Health |
Inspection | 1237123 | Yes | ||
Accident | 1209210 | |||
Inspection | 1237331 | Yes | ||
Inspection | 1246152 | Yes | ||
Inspection | 1236138 | Yes | ||
Inspection | 1229973 | Yes | ||
Inspection | 1236056 | Yes | ||
Inspection | 1237187 | Yes | ||
Inspection | 1236050 | Yes | ||
Inspection | 1237328 | Yes |
Case Status: CLOSED |
Serious | Willful | Repeat | Other | Unclass | Total | |
---|---|---|---|---|---|---|
Initial Violations | 1 | 1 | ||||
Current Violations | 1 | 1 | ||||
Initial Penalty | $12,675 | $0 | $0 | $0 | $0 | $12,675 |
Current Penalty | $12,675 | $0 | $0 | $0 | $0 | $12,675 |
FTA Amount | $0 | $0 | $0 | $0 | $0 | $0 |
# | ID | Type | Standard | Issuance | Abate | Curr$ | Init$ | Fta$ | Contest | LastEvent | |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 5A0001 | 11/01/2017 | 12/20/2017 | $12,675 | $12,675 | $0 | 11/27/2017 | F - Formal Settlement |
Accident Investigation Summary | ||||||
---|---|---|---|---|---|---|
Summary Nr: 95263.015 | Event: 05/03/2017 | Employee Is Struck By Vehicle And Is Killed | ||||
At 10:00 a.m. on May 3, 2017, an employee was standing when they were struck by a vehicle and was killed. No further specifics were included in the initial rep ort. | ||||||
Keywords: motor vehicle, struck by, traffic accident, vehicle | ||||||
Inspection | Degree | Nature | Occupation | |||
1 | 1229944.015 | Fatality | Laborers, except construction |