Inspection Detail
Inspection: 120289723 - P G & E
Inspection Information - Office: American Canyon District Office
Site Address:
P G & E
Mountain View Avenue
Laguitas, CA 94938
Mailing Address:
303 Carlson Street, Vallejo, CA 94589
Union Status: Union
SIC:4931
NAICS: 0
Inspection Type: Accident
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 01/26/1995
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 03/27/1995
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 362133555 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 2 | 2 | ||||
| Initial Penalty | $10,000 | $0 | $0 | $0 | $0 | $10,000 |
| Current Penalty | $10,000 | $0 | $0 | $0 | $0 | $10,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 2941 I02 | 01/26/1995 | 01/12/1995 | $5,000 | $5,000 | $0 | 02/10/1995 | F - Formal Settlement | |
| 2. | 02001 | Serious | 2941 I05 | 01/26/1995 | 01/12/1995 | $5,000 | $5,000 | $0 | 02/10/1995 | F - Formal Settlement |
Investigation Summary
A power line crew was repairing an overhead power line that had been damaged in a storm. The crew foreman was in the bucket of a one-person bucket aerial lift to install the power line on a utility pole. A power line worker was preparing to hoist the downed line to the foreman. The 12-kilovolt power line was deenergized when the crew arrived. However, the crew did not install protective grounds, nor did they place tags on the disconnection point. A troubleman was sent to the general area in response to outage reports. When he found no tags at the disconnection point, the troubleman reenergized the line to see if the fault was still present. When the line was reenergized, the power line worker, who was touching the power line, received an electric shock. He was hospitalized with burns up to third-degree on his left arm and right hand.
Keywords: BURN, OVERHEAD POWER LINE, PROTECTIVE GROUNDING, ELECTRICAL, POWER LINE WORKER, LOCKOUT, E PTD, ELEC UTILITY WORK, ELECTRIC SHOCK
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 120289723 | Hospitalized injury | Electric Shock | Electrical power installers and repairers |