Powered by GoogleTranslate

Occupational Safety and Health Administration OSHA

Inspection Detail

Inspection: 112131453 - Alflex Corp

Inspection Information - Office: Ca Long Beach District Office

Nr: 112131453Report ID: 0950635Open Date: 02/23/1994

Alflex Corp
2630 El Presidio St
Long Beach, CA 90810
Union Status: NonUnion
SIC: 3644/Noncurrent-Carrying Wiring Devices

Inspection Type:Accident
Scope:Partial Advanced Notice:N
Ownership:Private
Safety/Health:Safety Close Conference:08/02/1994
Planning Guide: Safety-Manufacturing Close Case:06/13/2007

Related Activity:TypeIDSafetyHealth
 Accident362022303    

Violation Summary
Serious Willful Repeat Other Unclass Total
Initial Violations 2 1 2 5
Current Violations 3 2 5
Initial Penalty $3,275 $62,500 $0 $560 $0 $66,335
Current Penalty $9,525 $0 $0 $560 $0 $10,085
FTA Amount $0 $0 $0 $0 $0 $0

Violation Items
# ID Type Standard Issuance Abate Curr$ Init$ Fta$ Contest LastEvent
  1. 01001 Other 23400022 A 08/02/1994 08/19/1994 $185 $185 $0 08/22/1994 J - ALJ Decision
  2. 01002 Other 2714 B 08/02/1994 08/02/1994 $375 $375 $0 08/22/1994 J - ALJ Decision
  3. 02001 Serious 3999 B 08/02/1994 08/02/1994 $935 $935 $0 08/22/1994 J - ALJ Decision
  4. 03001 Serious 2717 08/02/1994 08/02/1994 $2,340 $2,340 $0 08/22/1994 J - ALJ Decision
  5. 04001 Serious 2940 B 08/02/1994 08/02/1994 $6,250 $62,500 $0 08/22/1994 J - ALJ Decision

Accident Investigation Summary
Summary Nr: 170358485Event: 02/23/1994Electric Shock - Direct Contact With Energized Parts
An electrical manufacturing company was producing flexible cable. One of its products consisted of a coil of flexible cable containing three insulated circuit conductors. (The coils were about the size of a roll of garden hose.) Before being shipped, the cables were tested to ensure that the insulation on the conductors had not been damaged. A production tester at the company was using a Hipotronics AC Dielectric Test Set (Model No. 702-2, Part No. CS14-1159) to test the cables. The test set was mounted above a coil testing bench. The test was conducted by clamping one high voltage lead to the conductors and the other lead to the conduit. The test leads were then energized (to 1500 to 2000 volts depending on the product being tested) for 1 minute. If the current exceeded 1.1 amperes, the test set would trip out. After the test, the test leads were deenergized and disconnected. On this particular day, the employee conducting the test apparently contacted the leads while they were still energized and was electrocuted (per the coroner's report). He had been wearing work boots, safety glasses, ear plugs, a back support belt, and leather gloves. The gloves had what appeared to be a burn hole in one finger on each glove, and the employee had corresponding burn marks on his fingers. Witnesses heard the employee groan and saw him fall backward and hit his head on a conveyor on the way down. In May 1993 (9 to 10 months before the accident), the manufacturer of the test equipment recommended that the company enclose the test specimen and interlock the enclosure so that the leads could not be energized while the enclosure was open. The company had not followed this recommendation.
Keywords: e gi iv, electrical, electrical testing, electrocuted, lockout, test equipment, unguarded live parts, elec circ part--misc
Inspection Degree Nature Occupation
1 112131453 Fatality Electric Shock Production inspectors, checkers and examiners

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close