Inspection Detail
Inspection: 111840096 - L P Construction
Inspection Information - Office: American Canyon District Office
Site Address:
L P Construction
Fitch Mountain Rd. & Greens Dr.
Healdsburg, CA 95448
Mailing Address:
P.O. Box 492947, Redding, CA 96049
Union Status: NonUnion
SIC:1623
NAICS: 0
Inspection Type: Accident
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 10/18/1990
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 08/31/1993
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 361302524 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 3 | 4 | |||
| Current Violations | 1 | 3 | 4 | |||
| Initial Penalty | $0 | $12,000 | $0 | $250 | $0 | $12,250 |
| Current Penalty | $0 | $12,000 | $0 | $250 | $0 | $12,250 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 341 A | 10/17/1990 | 10/22/1990 | $250 | $250 | $0 | - | ||
| 2. | 01002 | Other | 1510 A | 10/17/1990 | 11/18/1990 | $0 | $0 | $0 | - | ||
| 3. | 01003 | Other | 1599 C | 10/17/1990 | 10/18/1990 | $0 | $0 | $0 | - | ||
| 4. | 02001 | Willful | 1540 D | 10/17/1990 | 10/18/1990 | $12,000 | $12,000 | $0 | 11/05/1990 | W - Empr Withdrew |
Investigation Summary
At approximately 2:00 p.m. on October 17, 1991, Employee #1, of LP Construction, was installing a water line in Healdsburg, CA. He was in a 7 ft by 3 ft by 7 ft deep trench that had been dug the previous day to expose a portion of the old water line that was to be removed. Employee #1 was using a power saw to cut the lateral pipe when the trench caved in on him. He sustained serious injuries and was transported by ambulance to Healdsburg General Hospital; he was later transferred to Santa Rosa Memorial Hospital. Nearly 2 months earlier, the city had faxed a memo to LP Construction about the lack of shoring in a trench over 5 ft deep. Employee #1 had worked in underground construction for 6 years and for LP Construction for 2 months.
Keywords: INSTALLING, WORK RULES, CONSTRUCTION, TRENCH, SHORING, CAVE-IN
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 111840096 | Hospitalized injury | Fracture | Construction laborers |