Inspection: 103022430 - Dalrymple Construction Co., Inc.

Inspection Information - Office: Cleveland Area Office

 

Inspection Nr: 103022430
Report ID: 0522300
Date Opened: 08/22/1990

Site Address:
Dalrymple Construction Co., Inc.
2532 South Applecreek Rd., Ati Swine Farm
Applecreek, OH 44606

Mailing Address:
1893 Millersburg Rd., Wooster, OH 44691

Union Status: NonUnion

SIC:1731

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 10/02/1990

Planning Guide: Safety-Construction

Emphasis:

Case Closed: 12/17/1990


Related Activity
Type Activity Nr Safety Health
Accident 360714356
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 8 2 2 12
Current Violations 8 2 2 12
Initial Penalty $4,600 $16,000 $0 $0 $0 $20,600
Current Penalty $3,220 $9,600 $0 $0 $0 $12,820
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19260059 E01 10/15/1990 12/05/1990 $350 $500 $0 I - Informal Settlement  
2. 01002 Serious 19260059 G01 10/15/1990 12/05/1990 $350 $500 $0 I - Informal Settlement  
3. 01003 Serious 19260059 H 10/15/1990 12/05/1990 $350 $500 $0 I - Informal Settlement  
4. 01004 Serious 19260556 B02 I 10/15/1990 10/31/1990 $420 $600 $0 I - Informal Settlement  
5. 01005 Serious 19260950 C01 I 10/15/1990 10/18/1990 $700 $1,000 $0 I - Informal Settlement  
6. 01006A Serious 19260950 E01 I 10/15/1990 12/05/1990 $350 $500 $0 I - Informal Settlement  
7. 01006B Serious 19260950 E01 II 10/15/1990 12/05/1990 $0 $0 $0 -  
8. 01007 Serious 19260951 A01 III 10/15/1990 10/18/1990 $420 $600 $0 I - Informal Settlement  
9. 01008 Serious 19260952 B02 10/15/1990 10/31/1990 $280 $400 $0 I - Informal Settlement  
10. 02001 Willful 19260021 B02 10/15/1990 10/31/1990 $4,800 $8,000 $0 I - Informal Settlement  
11. 02002 Willful 19260556 B02 V 10/15/1990 10/18/1990 $4,800 $8,000 $0 I - Informal Settlement  
12. 03001 Other 19040002 A 10/15/1990 12/05/1990 $0 $0 $0 -  
13. 03002 Other 19040004 10/15/1990 12/05/1990 $0 $0 $0 -  

Investigation Summary

Investigation Nr: 867515
Event: 08/20/1990
ELECTRIC SHOCK - DIRECT CONTACT WITH OVERHEAD LINE

AN OVERHEAD POWER LINE WAS BEING UPGRADED FROM 2400 VOLTS DELTA TO 7200 VOLTS. A NEW CROSSARM HAD BEEN INSTALLED ON THE UTILITY POLE, AND A NEW TRANSFORMER HAD BEEN PLACED ON THE POLE AS WELL. AN EMPLOYEE WORKING FROM A PITTMAN HYDRAULIC AERIAL LIFT WAS MOVING A PHASE CONDUCTOR ONTO THE NEW PIN INSULATOR ON THE CROSSARM. THE EMPLOYEE, WHO WAS NOT WEARING RUBBER INSULATING GLOVES, WAS ELECTROCUTED WHEN HE CONTACTED THE OVERHEAD LINE.

Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, ELEC UTILITY WORK, AERIAL LIFT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 103022430 Fatality Electric Shock Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.