Inspection Detail
Inspection: 807677 - Healy, Yonkers, Atlas-Gest J/V
Inspection Information - Office: Manhattan Area Office
Site Address:
Healy, Yonkers, Atlas-Gest J/V
Water Tunnel - Roosevelt Island
New York, NY 10044
Mailing Address:
P.O. Box 230 - Island Station, New York, NY 10044
Union Status: Union
SIC:1622
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 05/22/1985
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 08/22/1985
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 360514400 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 7 | 1 | 8 | |||
| Current Violations | 7 | 1 | 8 | |||
| Initial Penalty | $2,450 | $5,400 | $0 | $0 | $0 | $7,850 |
| Current Penalty | $1,825 | $2,700 | $0 | $0 | $0 | $4,525 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19260800 A06 | 07/15/1985 | 07/25/1985 | $360 | $480 | $0 | I - Informal Settlement | ||
| 2. | 01001B | Serious | 19260800 B01 | 07/15/1985 | 07/25/1985 | $0 | $0 | $0 | - | ||
| 3. | 01001C | Serious | 19260800 B03 | 07/15/1985 | 07/25/1985 | $0 | $0 | $0 | - | ||
| 4. | 01001D | Serious | 19260800 E01 XII | 07/15/1985 | 08/08/1985 | $0 | $0 | $0 | - | ||
| 5. | 01002A | Serious | 19260800 C01 I | 07/15/1985 | 07/19/1985 | $300 | $400 | $0 | I - Informal Settlement | ||
| 6. | 01002B | Serious | 19260800 C01 II | 07/15/1985 | 07/19/1985 | $0 | $0 | $0 | - | ||
| 7. | 01003 | Serious | 19260800 B02 | 07/15/1985 | 07/19/1985 | $300 | $400 | $0 | I - Informal Settlement | ||
| 8. | 01004A | Serious | 19260800 C02 VII | 07/15/1985 | 07/24/1985 | $150 | $200 | $0 | I - Informal Settlement | ||
| 9. | 01004B | Serious | 19261000 B | 07/15/1985 | 07/19/1985 | $0 | $0 | $0 | - | ||
| 10. | 01005A | Serious | 19260800 H02 II | 07/15/1985 | 07/15/1985 | $315 | $420 | $0 | I - Informal Settlement | ||
| 11. | 01005B | Serious | 19260800 H02 IV | 07/15/1985 | 07/25/1985 | $0 | $0 | $0 | - | ||
| 12. | 01006 | Serious | 19260900 B | 07/15/1985 | 07/15/1985 | $150 | $200 | $0 | I - Informal Settlement | ||
| 13. | 01007 | Serious | 19260905 H | 07/15/1985 | 07/15/1985 | $250 | $350 | $0 | I - Informal Settlement | ||
| 14. | 02001 | Willful | 5A0001 | 07/15/1985 | 07/19/1985 | $2,700 | $5,400 | $0 | I - Informal Settlement |
Investigation Summary
EMPLOYEES #1 THROUGH #5 WERE WORKING IN A TUNNEL WHEN WATER, WHICH WAS CONTAINED IN A PLUGGED DROP SHAFT, WAS SUDDENLY RELEASED. THE EMPLOYEES WERE SWEPT ALONG THE TUNNEL FLOOR BY THE FLOOD OF WATER AND STONES. THEY WERE ALL HOSPITALIZED.
Keywords: TUNNEL, CONSTRUCTION, SHAFT, WATER
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 807677 | Hospitalized injury | Bruise/Contus/Abras | Occupation not reported | ||
| 2 | 807677 | Hospitalized injury | Cut/Laceration | Occupation not reported | ||
| 3 | 807677 | Hospitalized injury | Bruise/Contus/Abras | Occupation not reported | ||
| 4 | 807677 | Hospitalized injury | Bruise/Contus/Abras | Occupation not reported | ||
| 5 | 807677 | Hospitalized injury | Bruise/Contus/Abras | Occupation not reported |