Inspection: 314822032 - O.P. Handyman
Inspection Information - Office: Van Nuys District Office
Site Address:
O.P. Handyman
4595 Camino Del Mirasol
Santa Barbara, CA 93110
Mailing Address:
501 Andrea Dr., Oxnard, CA 93033
Union Status: NonUnion
SIC:1521
NAICS: 236115/New Single-Family Housing Construction (except Operative Builders)
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 09/03/2010
Emphasis:
Case Closed: 02/01/2015
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 102633716 | ||
Accident | 102633815 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 1 | 2 | 3 | |||
Current Violations | 3 | 3 | ||||
Initial Penalty | $18,000 | $0 | $0 | $520 | $0 | $18,520 |
Current Penalty | $0 | $0 | $0 | $780 | $0 | $780 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Other | 1509 A | 11/22/2010 | 12/23/2010 | $260 | $260 | $0 | 12/29/2010 | F - Formal Settlement | |
2. | 01002 | Other | 5194 E01 | 11/22/2010 | 12/23/2010 | $260 | $260 | $0 | 12/29/2010 | F - Formal Settlement | |
3. | 02001 | Other | 1534 B | 11/22/2010 | 12/23/2010 | $260 | $18,000 | $0 | 12/29/2010 | F - Formal Settlement |
Investigation Summary
At approximately 9:25 a.m. on August 30, 2010, Employee #1 was using Klean-Strip lacquer thinner, a flammable liquid, to remove linoleum adhesive from the floor of a laundry room. The laundry room was approximately 12 ft by 22 ft. It had a window (35.5 in. in height by 47.5 in. in width) and a door leading to the garage of the house and another door leading to the backyard. The laundry room was empty except for some built in cabinets, a water heater and solar storage tank. While Employee #1 used the flammable lacquer, the room was unventilated with both doors closed and only the window open. As Employee #1 removed the adhesive, flammable vapors were created. The water heater with its electrical heating elements ignited the vapor and resulted in an explosion and flash fire. The explosion and fire struck Employee #1, causing second and third degree burns over 85 percent of his body. Emergency medical personnel were summoned. They arrived and transported him to a hospital where he was later airlifted to a burn center. He died at approximately 3:30 p.m. on the same day.
Keywords: BURN, FLAMMABLE LIQUID, FLAMMABLE VAPORS, CLEANING, FIRE, IGNITION SYSTEM
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 314822032 | Fatality | Burn(Chemical) | Construction laborers |