Inspection: 313162307 - Diversifed Utility Services Inc

Inspection Information - Office: Santa Ana District Office

 

Inspection Nr: 313162307
Report ID: 0950631
Date Opened: 09/23/2009

Site Address:
Diversifed Utility Services Inc
South El Camino Real/West Avenida Valencia
San Clemente, CA 92672

Mailing Address:
3105 Unicorn Rd, Bakersfield, CA 93308

Union Status: Union

SIC:1731

NAICS: 238210/Electrical Contractors


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 02/03/2010

Planning Guide: Safety-Construction

Emphasis:

Case Closed: 08/15/2012


Related Activity
Type Activity Nr Safety Health
Accident 102587912
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 1 3
Current Violations 2 1 3
Initial Penalty $27,000 $0 $0 $900 $0 $27,900
Current Penalty $14,100 $0 $0 $900 $0 $15,000
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Other 1509 A 02/04/2010 02/09/2010 $900 $900 $0 02/11/2010 W - Empr Withdrew  
2. 02001 Serious 2940 D01 02/04/2010 02/09/2010 $4,000 $9,000 $0 02/11/2010 F - Formal Settlement  
3. 03001 Serious 2941 F01 B 02/04/2010 02/09/2010 $10,100 $18,000 $0 02/11/2010 F - Formal Settlement  

Investigation Summary

Investigation Nr: 202550661
Event: 09/22/2009
Lineman Is Electrocuted

On September 22, 2009, two 4-men crews with a company that repairs, maintains, and services electrical power distribution lines were replacing an old electrical utility pole with a new one. This pole had both 12KV and 4KV transmission lines. They had cut the old pole at the bottom, moved it slightly, and secured the old pole to the new one. They had also transferred the 12KV lines on the top arm from the old pole to the new pole. Employee #1 (an apprentice lineman) and a coworker (a journeyman lineman) were elevated in a bucket working on the 4KV lines. They had already transferred and tied up 4KV phases A and C from the old pole to the new pole and were tying up phase B. They were using line hoses (guts) to cover the live transmission lines on both sides of the double cross-arm. The energized conductors (lines and the tie wires) on top of the cross-arm were not covered. There were sections (approximately 13 in. long) of energized 4KV conductors of all three phases uncovered between the pairs of insulators on the double cross-arm. The distance between the parallel phase lines was about 18 in. Employee #1 had slid back the line hose on phase B to uncover a long portion (approximately 10 in. long) of the line next to the cross arm to facilitate wrapping of tie wire to the phase line. While attempting to tie up phase B, Employee #1 contacted the uncovered phase B line with his right elbow and an uncovered phase A conductor on top of the cross-arm with his left elbow. He was electrocuted.

Keywords: BOOM TRUCK, ELECTRICIAN, ELECTROCUTED, LOCKOUT, INEXPERIENCE, ELBOW

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 313162307 Fatality Electric Shock Electricians' apprentices
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.