Inspection: 310202197 - San Cristobal Distributing

Inspection Information - Office: Van Nuys District Office

 

Inspection Nr: 310202197
Report ID: 0950643
Date Opened: 06/23/2008

Site Address:
San Cristobal Distributing
20991 South Mountain Rd.
Santa Paula, CA 93060

Mailing Address:
3645 Saviers Rd., Ste. 14, Oxnard, CA 93033

Union Status: NonUnion

SIC:0161

NAICS: 111219/Other Vegetable (except Potato) and Melon Farming


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 12/19/2008

Emphasis:

Case Closed: 10/02/2012


Related Activity
Type Activity Nr Safety Health
Accident 102540788
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 1 2 3
Current Violations 3 3
Initial Penalty $15,750 $0 $0 $670 $0 $16,420
Current Penalty $0 $0 $0 $7,670 $0 $7,670
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Other 341 C01 12/19/2008 01/06/2009 $560 $560 $0 01/15/2009 F - Formal Settlement  
2. 01002 Other 1509 B 12/19/2008 01/05/2009 $110 $110 $0 01/15/2009 J - ALJ Decision  
3. 02001 Other 5418 C 12/19/2008 12/29/2008 $7,000 $15,750 $0 01/15/2009 J - ALJ Decision  

Investigation Summary

Investigation Nr: 202466132
Event: 06/22/2008
Employee Is Killed and Others Burned in Drum Explosion

On June 22, 2008, Employees #1, #2, #3 and #4 were creating a drainage system for the farm. This drainage system would divert water away from a ravine. The water would be collected in a sump. The employees were directed to install the drainage system by the owner of the company and the owner's wife. The owner stated that he had requested the employees to excavate a sump and install a plastic lining to be purchased from a hardware store. According to the employees, the owner told them to utilize the 55 gallon drums located on the property at part of the sump system. The drums were to be cut on the side to insert piping into the drums. The employees were in the welding shed at the time of the incident. Based on the interviews conducted, the employees operating the Oxy-Acetylene torch system utilized the system to attempt to cut a hole in the barrel. The drum was not cleaned and no measures were taken to ensure that the drum was free of ignitable chemicals. The volatile organic compounds within the barrel were ignited by the torch. The resulting fire burned all 6 injured persons. Employee #2 was killed. Employees #1, #3 and #4 were hospitalized for burns. Interviews were conducted of three remaining employees, the owner and fire investigator. The investigation concluded that the drum containing Volatile organic compounds was ignited by the Oxy-Acetylene system as the flame approached the drum.

Keywords: BURN, DRUM, WELDER, EXPLOSION

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 310202197 Hospitalized injury Burn/Scald(Heat) Laborers, except construction
2 310202197 Fatality Burn/Scald(Heat) Laborers, except construction
3 310202197 Hospitalized injury Burn/Scald(Heat) Laborers, except construction
4 310202197 Hospitalized injury Burn/Scald(Heat) Laborers, except construction
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.