Inspection Detail

Inspection: 310100706 - Membrane Technology & Research

Inspection Information - Office: Foster City District Office

 

Inspection Nr: 310100706
Report ID: 0950613
Date Opened: 09/02/2011

Site Address:
Membrane Technology & Research
1360 Willow Road
Menlo Park, CA 94025

Mailing Address:
1360 Willow Road, Menlo Park, CA 94025

Union Status: NonUnion

SIC:3569

NAICS: 333999/All Other Miscellaneous General Purpose Machinery Manufacturing


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 02/23/2012

Emphasis:

Case Closed: 12/22/2015


Related Activity
Type Activity Nr Safety Health
Accident 101138295
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 6 2 8
Current Violations 5 2 7
Initial Penalty $55,350 $0 $0 $500 $0 $55,850
Current Penalty $33,075 $0 $0 $500 $0 $33,575
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Other 3203 A07 C 02/24/2012 03/10/2012 $250 $250 $0 03/05/2012 F - Formal Settlement  
2. 01002 Other 4649 D 02/24/2012 03/10/2012 $250 $250 $0 03/05/2012 F - Formal Settlement  
3. 02001 Serious 560 A03 02/24/2012 03/10/2012 $0 $16,200 $0 03/05/2012 F - Formal Settlement Citation has been deleted.
4. 03001 Serious 3203 A04 02/24/2012 03/10/2012 $225 $2,250 $0 03/05/2012 F - Formal Settlement  
5. 04001 Serious 3304 B 02/24/2012 03/10/2012 $225 $16,200 $0 03/05/2012 F - Formal Settlement  
6. 05001 Serious 4657 A07 02/24/2012 03/10/2012 $16,200 $2,250 $0 03/05/2012 F - Formal Settlement  
7. 06001 Serious 3328 A 02/24/2012 03/10/2012 $16,200 $16,200 $0 03/05/2012 F - Formal Settlement  
8. 07001 Serious 4649 A 02/24/2012 03/10/2012 $225 $2,250 $0 03/05/2012 F - Formal Settlement  

Investigation Summary

Investigation Nr: 201128634
Event: 09/02/2011
Employee Suffers Fatal Injuries from a Gas Cylinder Explosio

On September 2, 2011, Employee #1 of Membrane Technology & Research filled up a Matheson 1F gas cylinder approximately 15 inches in diameter and 45 inches tall with 1% Butane, 2% Helium, 20% Nitrogen and 78% Methane. With this concentration, the cylinder's pressure was 700 to 800 psi. The maximum capacity allowable working pressure for this originally propane cylinder is 300 psi and the pressure relief valve would only release pressure at or above 3360 psi. At approximately 3:40 pm, Employee #1 proceeded to fill up this Matheson 1F gas cylinder with more Methane from a 1700 psi cylinder tank. The employer's goal was to increase the Methane concentration in the Matheson 1F to be at 90% Methane and at an approximate pressure greater than 1200 psi. The pressure relief valve did not release pressure above the maximum capacity of this cylinder. The Matheson 1F gas cylinder accumulated pressure to approximately 800 to 900 psi and it exploded to pieces due to over-pressurization. Employee #1 that was filling this tank was blown 15 feet away to the adjoining laboratory and suffered fatal injuries.

Keywords: CYLINDER, GAS, EXPLOSION, PRESSURE RELEASE

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 310100706 Fatality Other Physical scientists, n.e.c.
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.