Inspection: 310093000 - Coastal Circuits

Inspection Information - Office: Foster City District Office

 

Inspection Nr: 310093000
Report ID: 0950613
Date Opened: 09/25/2007

Site Address:
Coastal Circuits
1602 Tacoma Way
Redwood City, CA 94063

Mailing Address:
, , 00000

Union Status: NonUnion

SIC:3471

NAICS: 332813/ Electroplating, Plating, Polishing, Anodizing, and Coloring


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 02/01/2008

Emphasis:

Case Closed: 04/20/2009


Related Activity
Type Activity Nr Safety Health
Accident 101130367
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 1 1
Current Violations 1 1
Initial Penalty $1,800 $0 $0 $0 $0 $1,800
Current Penalty $1,800 $0 $0 $0 $0 $1,800
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 3480 A 02/01/2008 02/06/2008 $1,800 $1,800 $0 02/25/2008 F - Formal Settlement  

Investigation Summary

Investigation Nr: 201126414
Event: 09/23/2007
Employee Drowns in Acid Tank

At 3:00 a.m. on Sunday, September 23, 2007, Employee #1 was working alone on the Saturday evening swing shift. His father, who also worked at the plant, became worried when his son did not return home from his shift. He went to the plant at approximately 1:00 a.m. and reportedly found him immersed head first in a small rinse tank (18 ft. wide x 24 ft. long x 36 ft. deep) on the plating line. Employee #1's father phone for help. Redwood City EMTs responded and pronounced Employee #1 dead at the site. Employee #1's typical shift was the graveyard shift from 12:30 a.m. to 9:00 a.m.. On the evening of September 22nd, he was asked to come in to run the plating line for a special order. According to the company staff, he was supposed to work only from 2:00 p.m. to 6:00 p.m.. However, he was reported by a coworker to be still working at 6:00 p.m. when she left. Employee #1's copper plating log indicates that he actually began work at around 12:00 Noon. His last entry on the log was 4:40 p.m. At about 6PM, he had a conversation with a coworker as she was leaving work. Thiscoworker was the last person remaining in the plant besides Employee #1, After she left, he was working alone. Sometime after Employee #1's coworker left the premises, Employee #1 did return to the plating line. His plating log shows that he had last extricated circuit boards from tank number 3 at 4:40 p.m. At some time later, Employee #1 placed 6 plates in a 5 minute hydrochloric acid tank (#110) at the head of the small tank line. According to the plating schedule that Employee #1 knew well, he would have then removed those and placed them in a one minute rinse tank (#111) immediately adjacent to #110. Employee #1 would have then placed 6 more plates in the #110 tank. Those plates were still in their respective tanks, and there was no other work in any of the small acid rinse tanks or the larger plating tanks when the manager and the emergency response personnel arrived later the next morning. When Employee #1 was found, he was not wearing his safety glasses. They were hanging on the wall above the work table. At autopsy, showed there was no sign of chemical burns to either eye. He was not wearing a respirator or face shield. Some edema from a white area about the size of a quarter was found in his throat, but the coroner believed that it was not likely the result of a concentrated acid, such as might have come from tank #110. He was also not wearing his smock. There was considerable erythema on the face and upper torso. The coroner concluded that the erythema was the result of his immersion in the tank. There were some abrasions of his left shoulder, most likely resulting from his efforts to extricate himself from the tank. At the time of the accident, the distance from the walking and working surface of the plating line to the top of the line of small tanks was approximately 24 inches. Distance from the top of the larger plating tanks was from 27 to 32 inches. Measurements did show that just below the copper plating line where Employee #1 worked, an ammonia etch operation was giving off ammonia vapors in concentrations high enough to be quite irritating depending on exposure position. One particular source point, which was not a regular work station, was found and shown to management for remediation.

Keywords: EYE, THROAT, AMMONIA, SAFETY BELT, HYDRAULIC CYLINDER, NECK, DROWN, FACE, RESPIRATOR

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 310093000 Fatality Asphyxia Metal plating machine operators
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.