Inspection: 3053949 - City Of New Bern Electrical Services Department

Inspection Information - Office: Nc Department Of Labor - Raleigh

 

Inspection Nr: 3053949
Report ID: 0453710
Date Opened: 08/05/1986

Site Address:
City Of New Bern Electrical Services Department
3219 Oaks Rd
New Bern, NC 28560

Mailing Address:
P O Box 1129, New Bern, NC 28560

Union Status: NonUnion

SIC:4911

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: StateGovt

Safety/Health: Safety

Close Conference: 08/11/1986

Emphasis:

Case Closed: 12/31/1989


Related Activity
Type Activity Nr Safety Health
Accident 360769020
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 1 1
Current Violations 1 1
Initial Penalty $0 $0 $0 $0 $0 $0
Current Penalty $0 $0 $0 $0 $0 $0
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19260400 C01 10/20/1986 11/24/1986 $0 $0 $0 -  

Investigation Summary

Investigation Nr: 14251987
Event: 08/04/1986
ELECTRIC SHOCK - DIRECT CONTACT WITH OVERHEAD LINE

A WORKER AND HIS FOREMAN RESPONDED TO A SERVICE CALL AT A RESIDENCE TO CHECK A COMPLAINT OF LOW VOLTAGE. UPON ARRIVING AT THE RESIDENCE, THE WORKER ENTERED AN AERIAL LIFT (A LINESMAN II, HI-RANGER MODEL 5FI 48PBI, SERIAL NO. 128011214, MOUNTED ON A CHEVROLET 7000 TRUCK). THE INSULATED LIFT HAD BEEN TESTED 2 MONTHS EARLIER AT 345 KILOVOLTS. THE EMPLOYEE POSITIONED HIMSELF IN THE AERIAL LIFT BUCKET BESIDE THE SECONDARY LINES ON THE UTILITY POLE. HE DETERMINED THAT THE VOLTAGE DROP WAS DUE TO A BAD SERVICE CONNECTION, POSSIBLY CAUSED BY CORRODED AND DIRTY CONDUCTORS AT THE CONNECTION. THE THREE CONDUCTORS OF THE 120-VOLT-TO-GROUND SERVICE DROP WERE DISCONNECTED AND CLEANED. THE EMPLOYEE HAD RECONNECTED TWO OF THE THREE CONDUCTORS AND WAS IN THE PROCESS OF CONNECTING THE THIRD WHEN ONE OF THE TWO RECONNECTED CONDUCTORS CONTACTED THE LEFT SIDE OF HIS BODY WHILE HE WAS HOLDING THE THIRD ONE. THE FOREMAN LOOKED UP, NOTICED THE EMPLOYEE SHAKING, AND LOWERED THE AERIAL LIFT. THE RESUCE SQUAD WAS CALLED AND RESPONDED TO THE SCENE WITHIN TWO MINUTES. THE RESCUE SQUAD BEGAN CARDIO-PULMONARY RESUSCITATION IMMEDIATELY, BUT THE EMPLOYEE WAS DEAD ON ARRIVAL AT THE HOSPITAL. HE HAD BEEN ELECTROCUTED.

Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, ELECTRICAL, CPR, ELECTROCUTED, E PTD, ELEC UTILITY WORK, AERIAL LIFT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 3053949 Fatality Electric Shock Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.