Inspection Detail
Inspection: 305350258 - Southern California Edison
Inspection Information - Office: Santa Ana District Office
Site Address:
Southern California Edison
445 E Coast Hwy
Newport Beach, CA 92660
Mailing Address:
14660 Chestnut St, Westminster, CA 92683
Union Status: Union
SIC:4911
NAICS: 221122/Electric Power Distribution
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: LocalGovt
Safety/Health: Safety
Close Conference: 09/30/2003
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 08/09/2006
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 362365637 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | ||||||
| Initial Penalty | $0 | $0 | $0 | $1,200 | $0 | $1,200 |
| Current Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 23200002 A01 | 09/30/2003 | 10/03/2003 | $0 | $600 | $0 | 10/08/2003 | F - Formal Settlement | Citation has been deleted. |
| 2. | 01002 | Other | 23200002 A04 | 09/30/2003 | 10/03/2003 | $0 | $600 | $0 | 10/08/2003 | F - Formal Settlement | Citation has been deleted. |
Investigation Summary
On April 8, 2003, Employee #1 was working as an electrician for the utility Southern California Edison (SCE). He was installing an electric meter for a temporary power connection at a construction site. The old meter had been removed earlier, and it was being replaced by a meter with SCE Part Number 3416-009713. The post that held the temporary meter had been wired previously from a transformer box installed at ground level. When Employee #1 arrived at the site, there was no meter on the post, and the meter socket on the 5-foot-high wooden post was energized. This circuit was wired for 480 volts phase-to-phase and 277 volts phase-to-ground. Employee #1 stated that his training required that he bypass the circuit to deenergize the meter socket before installing a meter. Normally he did that, but this time he did not think it was necessary. He decided to install the new meter while the socket was energized. Employee #1 had barely brought the meter into contact with the socket, when the meter caught fire. The arc flash caused second- and third-degree burns to both of Employee #1's hands and first-degree burns to his face. He was hospitalized for two weeks. Employee #1 was not a contract employee.
Keywords: BURN, ELECTRIC ARC, ELECTRICAL, PPE, ELECTRICIAN, CONSTRUCTION, ELECTRIC METER, E C, E PTD, ELEC UTILITY WORK
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 305350258 | Hospitalized injury | Burn/Scald(Heat) | Electricians |