Inspection Detail
Inspection: 303676571 - Rci Construction Goup, Robison Construction, Inc.
Inspection Information - Office: Denver Area Office
Site Address:
Rci Construction Goup, Robison Construction, Inc.
46440 Poudre Canyon, #M2
Bellvue, CO 80512
Mailing Address:
P.O. Box 1730, Summer, WA 98390
Union Status: NonUnion
SIC:1622
NAICS: 0
Inspection Type: Referral
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Health
Close Conference: 05/24/2001
Emphasis: L:Conspace, L:Silica, N:Silica, S:Construction, S:Silica
Case Closed: 09/05/2001
Type | Activity Nr | Safety | Health |
---|---|---|---|
Referral | 201575214 | Yes | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 9 | 9 | ||||
Current Violations | 9 | 9 | ||||
Initial Penalty | $31,950 | $0 | $0 | $0 | $0 | $31,950 |
Current Penalty | $23,950 | $0 | $0 | $0 | $0 | $23,950 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19260055 A | 05/25/2001 | 05/29/2001 | $4,725 | $6,300 | $0 | I - Informal Settlement | ||
2. | 01001B | Serious | 19260055 B | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
3. | 01001C | Serious | 19100134 A01 | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
4. | 01002 | Serious | 19100134 H03 IV | 05/25/2001 | 05/29/2001 | $1,350 | $1,800 | $0 | I - Informal Settlement | ||
5. | 01003 | Serious | 19260059 H | 05/25/2001 | 05/29/2001 | $1,350 | $1,800 | $0 | I - Informal Settlement | ||
6. | 01004 | Serious | 19260800 D | 05/25/2001 | 05/29/2001 | $3,375 | $4,500 | $0 | I - Informal Settlement | ||
7. | 01005 | Serious | 19260800 E01 | 05/25/2001 | 05/29/2001 | $1,010 | $1,350 | $0 | I - Informal Settlement | ||
8. | 01006 | Serious | 19260800 F04 | 05/25/2001 | 05/29/2001 | $2,360 | $3,150 | $0 | I - Informal Settlement | ||
9. | 01007A | Serious | 19260800 J01 IA | 05/25/2001 | 05/29/2001 | $3,375 | $4,500 | $0 | I - Informal Settlement | ||
10. | 01007B | Serious | 19260800 J01 IB | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
11. | 01007C | Serious | 19260800 J01 IIIA | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
12. | 01007D | Serious | 19260800 J01 IIID | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
13. | 01007E | Serious | 19260800 J01 VIB | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
14. | 01007F | Serious | 19260800 J03 | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
15. | 01008A | Serious | 19260800 K01 I | 05/25/2001 | 05/29/2001 | $4,725 | $6,300 | $0 | I - Informal Settlement | ||
16. | 01008B | Serious | 19260800 K03 | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
17. | 01008C | Serious | 19260800 K04 | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
18. | 01008D | Serious | 19260800 K10 | 05/25/2001 | 05/29/2001 | $0 | $0 | $0 | I - Informal Settlement | ||
19. | 01009 | Serious | 19260800 M07 | 05/25/2001 | 05/29/2001 | $1,680 | $2,250 | $0 | I - Informal Settlement |
Investigation Summary
Employee #1 was 3400 feet inside a tunnel conducting oxygen acetylene welding. He was overcome by carbon monoxide and later taken by life flight to the local hospital where he was diagnosed with carbon monoxide poisoning. Employee #1 was hospitalized for his injury.
Keywords: OXYGEN, ACETYLENE, WELDING, POISONING, CARBON MONOXIDE
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 303676571 | Hospitalized injury | Poisoning(Systemic) | Welders and cutters |