Inspection Detail
Inspection: 303264576 - Ron Trombly Construction
Inspection Information - Office: Nv-E-Reno 0953210
Site Address:
Ron Trombly Construction
2215 Driscoll Dr.
Reno, NV 89509
Mailing Address:
1742 Shaber Ave., Sparks, NV 89431
Union Status: NonUnion
SIC:1521
NAICS: 0
Inspection Type: Unprog Rel
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 02/07/2000
Planning Guide: Safety-Construction
Emphasis: N:Trench, S:Construction
Case Closed: 03/30/2000
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 361237415 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 3 | ||||
| Current Violations | 3 | 3 | ||||
| Initial Penalty | $3,000 | $0 | $0 | $0 | $0 | $3,000 |
| Current Penalty | $3,000 | $0 | $0 | $0 | $0 | $3,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19260021 B02 | 03/02/2000 | 03/07/2000 | $750 | $750 | $0 | I - Informal Settlement | ||
| 2. | 01001B | Serious | 19260651 K01 | 03/02/2000 | 03/07/2000 | $0 | $0 | $0 | - | ||
| 3. | 01002A | Serious | 19260651 C02 | 03/02/2000 | 03/07/2000 | $750 | $750 | $0 | I - Informal Settlement | ||
| 4. | 01002B | Serious | 19260651 J01 | 03/02/2000 | 03/07/2000 | $0 | $0 | $0 | - | ||
| 5. | 01002C | Serious | 19260651 J02 | 03/02/2000 | 03/07/2000 | $0 | $0 | $0 | - | ||
| 6. | 01003 | Serious | 19260652 A01 | 03/02/2000 | 03/07/2000 | $1,500 | $1,500 | $0 | I - Informal Settlement |
Investigation Summary
Employee #1 was digging out an approximately 14 to 15 ft deep trench when the walls caved in. He was buried up to his nose at one point, and it took rescue crews approximately four hours to free him. Employee #1 suffered a strained knee, but was not hospitalized. The trench was being dug in Class C soil. No shoring of any kind was provided.
Keywords: KNEE, WORK RULES, CONSTRUCTION, TRENCH, SHORING, BURIED, CAVE-IN
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 303264576 | Non Hospitalized injury | Strain/Sprain | Occupation not reported |