Powered by GoogleTranslate

Inspection Detail

Inspection: 302001235 - Ere Yarmouth Retail, Inc. Dba Colonie Center

Inspection Information - Office: Albany Area Office

 

Inspection Nr: 302001235
Report ID: 0213100
Date Opened: 02/17/1998

Site Address:
Ere Yarmouth Retail, Inc. Dba Colonie Center
131 Colonie Center
Albany, NY 12205

Mailing Address:
, , 00000

Union Status: NonUnion

SIC:6512

NAICS: 0 


Inspection Type: Referral

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 03/09/1998

Emphasis:

Case Closed: 07/01/1998


Related Activity
Type Activity Nr Safety Health
Referral 200741619 Yes
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 3 1 4
Current Violations 2 2 4
Initial Penalty $10,350 $0 $0 $0 $0 $10,350
Current Penalty $5,850 $0 $0 $0 $0 $5,850
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100147 C01 03/16/1998 04/18/1998 $2,925 $4,500 $0 I - Informal Settlement  
2. 01002 Other 19100157 G02 03/16/1998 04/18/1998 $0 $1,350 $0 I - Informal Settlement  
3. 01003A Serious 19100332 B01 03/16/1998 03/26/1998 $2,925 $4,500 $0 I - Informal Settlement  
4. 01003B Serious 19100333 A01 03/16/1998 03/26/1998 $0 $0 $0 -  
5. 01003C Serious 19100333 B02 03/16/1998 03/26/1998 $0 $0 $0 -  
6. 02001 Other 19040005 A 03/16/1998 03/26/1998 $0 $0 $0 -  

Investigation Summary

Investigation Nr: 200740298
Event: 02/16/1998
burn - electrical fault in panelboard

An engineer and a junior engineer working for a shopping mall went to the roof of the mall to investigate a problem with the air handler unit. They opened the disconnect box and discovered that the three-phase, 480-volt disconnect needed to be replaced. The engineer called a supply store, but an exact replacement was not in stock. He remembered that there were two spares in the main panelboard area in the electrical room. He decided to pull one out and use it for the air handler. The engineer removed cover from the main panelboard without deenergizing it. He asked for a flashlight, and his assistant gave it to him and turned around to read some gauges. The engineer, who had a screwdriver in one hand, was looking in the back of the panelboard with the flashlight when an electrical fault occurred. The ensuing electric arc burned the engineer and threw him 4.5 to 6.0 meters away. The shaft on the screwdriver showed signs of melting after the accident. The junior engineer put out the fire with a fire extinguisher and helped the injured employee off the floor and to the office. The engineer was hospitalized for his injuries.

Keywords: BURN, ELECTRIC ARC, E GI IV, ELECTRICAL, ELECTRICIAN, PANELBOARD, ELECTRICAL WORK, LOCKOUT, ELECTRICAL FAULT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 302001235 Hospitalized injury Burn/Scald(Heat) Industrial engineering technicians
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close