Inspection Detail
Inspection: 300780848 - Pervo Paint Company
Inspection Information - Office: Long Beach District Office
Site Address:
Pervo Paint Company
6624 Stanford Ave
Los Angeles, CA 90001
Mailing Address:
, , 00000
Union Status: NonUnion
SIC:2851
NAICS: 325510/Paint and Coating Manufacturing
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/01/2003
Emphasis:
Case Closed: 07/05/2006
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 101053502 | ||
| Accident | 362507824 | ||
| Accident | 362507840 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 4 | 7 | 11 | |||
| Current Violations | 4 | 7 | 11 | |||
| Initial Penalty | $24,295 | $0 | $0 | $3,220 | $0 | $27,515 |
| Current Penalty | $24,295 | $0 | $0 | $3,220 | $0 | $27,515 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 5144 F02 | 08/01/2003 | 08/26/2003 | $205 | $205 | $0 | - | ||
| 2. | 01002 | Other | 3203 A06 | 08/01/2003 | 08/26/2003 | $615 | $615 | $0 | - | ||
| 3. | 01003 | Other | 3209 A | 08/01/2003 | 08/26/2003 | $480 | $480 | $0 | - | ||
| 4. | 01004 | Other | 3234 E01 | 08/01/2003 | 08/26/2003 | $480 | $480 | $0 | - | ||
| 5. | 01005 | Other | 3301 A | 08/01/2003 | 08/26/2003 | $480 | $480 | $0 | - | ||
| 6. | 01006 | Other | 5162 D | 08/01/2003 | 08/26/2003 | $480 | $480 | $0 | - | ||
| 7. | 01007 | Other | 5162 E | 08/01/2003 | 08/26/2003 | $480 | $480 | $0 | - | ||
| 8. | 02001 | Serious | 23950070 | 08/01/2003 | 08/26/2003 | $3,710 | $3,710 | $0 | - | ||
| 9. | 03001 | Serious | 4070 A | 08/01/2003 | 08/26/2003 | $3,710 | $3,710 | $0 | - | ||
| 10. | 04001 | Serious | 23400023 | 08/01/2003 | 08/26/2003 | $2,475 | $2,475 | $0 | - | ||
| 11. | 05001 | Serious | 5416 C | 08/01/2003 | 08/26/2003 | $14,400 | $14,400 | $0 | - |
Investigation Summary
At about 9:40 a.m. on February 4, 2003, Employee #1, a paint batch maker with Pervo Paint Company, was using a pebble mill to mix formulations of paint. This mill was a 1,000-gallon cylinder partially filled with approximately 8-inch pebbles and was loaded from the top from a platform that is 11 ft above the ground. To guide the components into the metal tank, a metal funnel is placed on top of the tank and the components are poured through the funnel. After the Pebble Mill is loaded, the top is closed and the mill is rotated and the pebbles mix and grind the components together. Employee #1 had charged the mill with approximately 120 gallons of acetone and 44 gallons of Xylene. He then poured bags of Chlorez 700, a chlorinated paraffin powder, into the tank. As he was pouring the sixteenth bag into the mill, an explosion occurred inside the tank. Employee #1 was thrown off of his feet and covered with a hot resin that emitted from the tank. The funnel to the tank was blown off as was part of the roof to the platform on which Employee #1 was standing. He was hospitalized first at L.A. County Martin Luther King Hospital, and then transferred to the Burn Unit at L.A. County General Hospital, with second and third degree burns on his face, chest, right arm and right leg, and suffered right eye and respiratory injury. The following causes for the accident were derived from the investigation: The operation was not tested for levels of flammability, the components of the operation were not bonded, and ignition sources were not controlled.
Keywords: BURN, FLAMMABLE LIQUID, MILLING MACHINE, PAINT, EXPLOSION
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 300780848 | Hospitalized injury | Burn/Scald(Heat) | Laborers, except construction |
Translate