Inspection Detail

Inspection: 300768785 - Union Power Construction Company

Inspection Information - Office: Nv-E-Las Vegas 0953220

 

Inspection Nr: 300768785
Report ID: 0953220
Date Opened: 05/28/1997

Site Address:
Union Power Construction Company
Edmond North Of Sunset/South Of Patrick
Las Vegas, NV 89118

Mailing Address:
4415 Andrew Street, North Las Vegas, NV 89031

Union Status: NonUnion

SIC:1531

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 09/26/1997

Planning Guide: Safety-Manufacturing

Emphasis:

Case Closed: 01/05/1998


Related Activity
Type Activity Nr Safety Health
Accident 101040343
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 1 3
Current Violations 1 1 2
Initial Penalty $5,000 $0 $0 $500 $0 $5,500
Current Penalty $2,500 $0 $0 $500 $0 $3,000
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001A Serious 19100269 A02 IIC 10/21/1997 11/17/1997 $0 $2,500 $0 I - Informal Settlement Citation has been deleted.
2. 01001C Serious 19100269 A02 III 10/21/1997 11/17/1997 $0 $0 $0 I - Informal Settlement Citation has been deleted.
3. 01002A Serious 19100269 P04 I 10/21/1997 10/24/1997 $2,500 $2,500 $0 I - Informal Settlement  
4. 01002B Serious 19100269 P04 IIIA 10/21/1997 10/24/1997 $0 $0 $0 I - Informal Settlement  
5. 01002C Serious 19100269 A02 IID 10/21/1997 11/17/1997 $0 $0 $0 I - Informal Settlement  
6. 02001 Other 618038301 10/21/1997 12/09/1997 $500 $500 $0 I - Informal Settlement  

Investigation Summary

Investigation Nr: 201040334
Event: 05/28/1997
ELECTRIC SHOCK - CONTACT WITH OVERHEAD LINE

Two power line workers were working from a two-person aerial lift. They were removing the static line above a deenergized, three-phase, 230-kilovolt overhead power line. The static line was located about 34 meters above the ground. The deenergized line was on the east side of the supporting towers, and an energized three-phase, 230-kilovolt overhead power line was on the west side of the towers. The static line was apparently energized by induction from the energized transmission line. The jumper on the bottom phase conductor had been protected by a polyethylene cover; however, this cover had been displaced, possibly because of movement of the platform or vibration. The boom on the aerial lift contacted the exposed jumper, and one of the power line workers was electrocuted.

Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, PROTECTIVE GROUNDING, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, INDUCED CURRENT, ELEC UTILITY WORK, AERIAL LIFT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 300768785 Fatality Electric Shock Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.