Inspection Detail

Inspection: 300564051 - Diamond Builders

Inspection Information - Office: Madison Area Office

 

Inspection Nr: 300564051
Report ID: 0523300
Date Opened: 10/17/1997

Site Address:
Diamond Builders
Adjacent To Mckee Street In Fitchburg
Fitchburg, WI 53593

Mailing Address:
245 Horizon Drive, Verona, WI 53593

Union Status: NonUnion

SIC:1751

NAICS: 0 


Inspection Type: Referral

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 11/07/1997

Emphasis:

Case Closed: 01/27/1998


Related Activity
Type Activity Nr Safety Health
Referral 200800092 Yes
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 2
Current Violations 1 1
Initial Penalty $2,100 $0 $0 $0 $0 $2,100
Current Penalty $600 $0 $0 $0 $0 $600
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 5A0001 11/12/1997 11/17/1997 $600 $1,500 $0 I - Informal Settlement Citation has been deleted.
2. 01002 Serious 19260021 B02 12/02/1997 12/05/1997 $600 $600 $0 I - Informal Settlement  

Investigation Summary

Investigation Nr: 200800050
Event: 10/16/1997
Two employees injured in fall when trusses collapse

Employees #1 and #2 were on a tubular welded-frame scaffold finishing the installation of the last of several 1,100 lb trusses, when one of them gave way, causing the others to fall. The collapsing landed on the scaffold, knocking off the two workers. Employees #1 and #2 sustained injuries, for which they were hospitalized. The two-piece scissor trusses were connected by a metal plate and joined together at the midpoint by two, 2 by 8s (one on either side of the midpoint) secured together with eight bolts. The trusses were also reinforced at the apex by plywood nailed into the 2 by 8 top plate and the two, 2 by 6s connecting the top and bottom cords. Altogether, the span of the trusses was 60 ft, and they were set 24 in. on center. The top cord had a slope of 10-in-12 and the bottom cord had a pitch of 5-in-12. According to the foreman, temporary continuous lateral bracing was installed in two places along both sides of the top plate, at about the center of the 40 ft long top plate. The foreman claimed that diagonal bracing had been installed along the top plate between the top cord lateral bracing. Permanent bracing was installed along the bottom cord and on both sides along the 2 by 8 intersecting and connecting the top and bottom cords. It was observed that top cord temporary bracing was installed using only one 16-penny nail. The foreman stated that there was some ground bracing on the south side of the structure, but no ground bracing along the north side. The Truss Plate Institute's guide recommended that at least 10 lengths of continuous lateral bracing be applied to the top cord of the size being set. The first of the continuous lateral bracing should have been installed on the top cord at the bearing point of the trusses along the side walls, and then at intervals of between 5 and 7 ft up to the peak. Top cord diagonal brace spacing should have been every five trusses, and all temporary bracing should have been installed using two fully seated 16-penny nails. According to the Truss Plate Institute's guidelines, grounding of both interior and exterior bracing is required. Other ground bracing of other erected trusses showed that the splices were connected with only three 16-penny nails. A minimum of ten, 3 1/4 in. nails was recommended for such splices. It was concluded that although permanent bracing (other than roof sheeting) had been installed along the interior cords and webs, temporary bracing was inadequate because of insufficient top cord lateral and diagonal bracing. The temporary braces were not nailed according to the Truss Plate Institute's recommendations. There was no ground bracing on the north side of the structure. A precipitating factor was the actual collapse and failure of one of the trusses. Questions have been raised on the engineering, design, and manufacture of the trusses being used. Analysis of the failed truss indicated that the metal king-post connection may not have been placed in an area which provided optimum support of the 2 by 12 bottom cord. Other trusses salvaged from the collapse revealed characteristics similar to those of the failed truss.

Keywords: ERECTION PROCESS, TRUSS, COLLAPSE, UNSECURED, WORK RULES, CONSTRUCTION, BRACE, FALL, BRACING, TUBULAR SCAFFOLD

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 300564051 Hospitalized injury Fracture Occupation not reported
2 300564051 Hospitalized injury Bruise/Contus/Abras Occupation not reported
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.