Inspection Detail
Inspection: 300476546 - Chief Supply Corp.
Inspection Information - Office: Oklahoma City Area Office
Site Address:
Chief Supply Corp.
7637 N.W. 3rd
Oklahoma City, OK 73127
Mailing Address:
, , 00000
Union Status: NonUnion
SIC:2999
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 04/10/1997
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 12/01/1998
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 100640531 | ||
| Referral | 200640399 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 9 | 1 | 10 | |||
| Current Violations | 9 | 1 | 10 | |||
| Initial Penalty | $26,500 | $0 | $50,000 | $0 | $0 | $76,500 |
| Current Penalty | $26,500 | $0 | $50,000 | $0 | $0 | $76,500 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19100023 A08 | 09/24/1997 | 09/29/1997 | $2,000 | $2,000 | $0 | 10/09/1997 | F - Formal Settlement | |
| 2. | 01001B | Serious | 19100023 C01 | 09/24/1997 | 09/29/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 3. | 01002A | Serious | 19100106 D04 I | 09/24/1997 | 09/29/1997 | $3,500 | $3,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 4. | 01002B | Serious | 19100106 H04 IC | 09/24/1997 | 09/29/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 5. | 01003 | Serious | 19100106 E05 II | 09/24/1997 | 10/27/1997 | $3,500 | $3,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 6. | 01004 | Serious | 19100106 H04 IIIA | 09/24/1997 | 09/28/1997 | $3,500 | $3,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 7. | 01005A | Serious | 19100146 C04 | 09/24/1997 | 10/27/1997 | $2,500 | $2,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 8. | 01005B | Serious | 19100146 E03 | 09/24/1997 | 09/28/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 9. | 01006A | Serious | 19100146 D14 | 09/24/1997 | 09/28/1997 | $2,500 | $2,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 10. | 01006B | Serious | 19100146 G01 | 09/24/1997 | 09/28/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 11. | 01007A | Serious | 19100146 K03 I | 09/24/1997 | 09/28/1997 | $2,500 | $2,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 12. | 01007B | Serious | 19100146 K03 II | 09/24/1997 | 09/28/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 13. | 01008 | Serious | 19100147 C01 | 09/24/1997 | 10/27/1997 | $5,000 | $5,000 | $0 | 10/09/1997 | F - Formal Settlement | |
| 14. | 01009A | Serious | 19100219 D01 | 09/24/1997 | 10/02/1997 | $1,500 | $1,500 | $0 | 10/09/1997 | F - Formal Settlement | |
| 15. | 01009B | Serious | 19100219 E03 I | 09/24/1997 | 10/02/1997 | $0 | $0 | $0 | 10/09/1997 | F - Formal Settlement | |
| 16. | 02001 | Repeat | 19100178 M11 | 09/24/1997 | 09/28/1997 | $50,000 | $50,000 | $0 | 10/09/1997 | F - Formal Settlement |
Investigation Summary
Employees #1 and #2, both production workers, were part of a team that was blending flammable organic solvent-based waste into waste kiln fuel. Production was up because a shipment needed to be transported soon, and Employees #1 and #2 were dumping drums of waste into blending dispersers. After emptying a previous batch out of the small disperser, its mixer wheel stopped running, so a lab worker, following a recently reinstated practice, poured approximately one gallon each of dry chlorates and perchlorates into the disperser's interior. The lab worker then went back to the laboratory and returned with a gallon of dry nitrites, which he also poured into the container. Employees #1 and #2 had, by this time, both moved on to new projects. Employee #2 was operating a forklift with an attached drum dumping fixture; Employee #1 was standing on the fixture, starting to dump another drum. The lab worker conversed briefly with Employee #2 and was starting to walk away when waste erupted from the top of the dispenser, followed by a large fireball. Both Employees #1 and #2 were sprayed by the burning waste; Employee #1's Tyvek suit caught fire, as did Employee #2's shirt collar. Some coworkers tried to help them, while others began fighting the flames before all the workers were evacuated. Employee #1 died of burns sustained in the accident; Employee #2 suffered burns to his neck but was not hospitalized. The fire ultimately destroyed the entire upper level of the plant. Its probable cause was the addition of the three different oxidizers to the flammable organic solvent-based waste. The three oxidizers reacted among themselves, and with the waste liquid, producing intense heat that ignited the waste's flammable vapors.
Keywords: FLAMMABLE VAPORS, WORK RULES, WASTE PROC FAC, EXPLOSION, BURN, HEAT, MIXER, CHEMICAL REACTION, MECH MALFUNCTION, CHEMICAL
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 300476546 | Fatality | Burn/Scald(Heat) | Occupation not reported |