Inspection Detail
Inspection: 300219391 - American Milling Lp
Inspection Information - Office: Peoria Area Office
Site Address:
American Milling Lp
1811 American
Pekin, IL 61554
Mailing Address:
P.O. Box 5005, Cahokia, IL 62206
Union Status: NonUnion
SIC:2048
NAICS: 0
Inspection Type: Referral
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 01/08/1999
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 02/17/1999
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Referral | 200270874 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 2 | 2 | ||||
| Initial Penalty | $1,750 | $0 | $0 | $0 | $0 | $1,750 |
| Current Penalty | $0 | $0 | $0 | $1,225 | $0 | $1,225 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19100023 C01 | 01/15/1999 | 03/05/1999 | $613 | $875 | $0 | I - Informal Settlement | ||
| 2. | 01002A | Other | 19100027 B01 III | 01/15/1999 | 03/05/1999 | $613 | $875 | $0 | I - Informal Settlement | ||
| 3. | 01002B | Other | 19100027 D03 | 01/15/1999 | 03/05/1999 | $0 | $0 | $0 | I - Informal Settlement |
Investigation Summary
Employee #1 was repairing some equipment on top of an outside tank when he fell to the ground. He suffered back and head injuries, for which he was hospitalized.
Keywords: HEAD, REPAIR, WORK RULES, STORAGE TANK, BACK, FALL, FALL PROTECTION, TANK
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 300219391 | Hospitalized injury | Fracture | Laborers, except construction |