Inspection Detail

Inspection: 18054569 - Columbus Southern Power Company

Inspection Information - Office: Cincinnati Area Office

 

Inspection Nr: 18054569
Report ID: 0522000
Date Opened: 06/26/1991

Site Address:
Columbus Southern Power Company
2290 Germany Hollow Road
Wheelersburg, OH 45694

Mailing Address:
3 West 13th Street, Wellston, OH 45692

Union Status: Union

SIC:4911

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: Y

Ownership: Private

Safety/Health: Safety

Close Conference: 07/01/1991

Planning Guide: Safety-Construction

Emphasis:

Case Closed: 05/14/1992


Related Activity
Type Activity Nr Safety Health
Accident 361108566
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 3 3
Current Violations 1 1
Initial Penalty $15,000 $0 $0 $0 $0 $15,000
Current Penalty $2,500 $0 $0 $0 $0 $2,500
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19260950 B01 07/11/1991 07/18/1991 $2,500 $5,000 $0 07/29/1991 F - Formal Settlement  
2. 01002 Serious 19260955 A04 07/11/1991 07/18/1991 $5,000 $5,000 $0 07/29/1991 F - Formal Settlement Citation has been deleted.
3. 01003 Serious 19260955 E11 07/11/1991 07/18/1991 $5,000 $5,000 $0 07/29/1991 F - Formal Settlement Citation has been deleted.

Investigation Summary

Investigation Nr: 14370993
Event: 06/24/1991
ELECTRIC SHOCK - CONTACT WITH OVERHEAD LINE THRU GUY

FOUR EMPLOYEES RESPONDED TO A REPORT OF A UTILITY POLE ON FIRE. THE EMPLOYEE NOTED THAT THE POLE WAS BURNED THREE QUARTERS OF THE WAY THROUGH THE POLE AT A POINT 2 FEET FROM THE TOP. THE EMPLOYEES HELD A JOB BRIEFING, WHICH FOCUSED MAINLY ON CONDITIONS AT THE TOP OF THE POLE. THE EMPLOYEES SET A NEW POLE ABOUT 6 FEET FROM THE OLD ONE. ONE OF THE EMPLOYEES WAS INSTALLING A NEW GUY, ATTACHING IT TO THE EXISTING ANCHOR ROD AND SECURING IT WITH A CHAIN JACK. THE OTHER EMPLOYEES WERE TRANSFERRING THE 7200-VOLT OVERHEAD LINE FROM THE OLD POLE TO THE NEW ONE. THEY HAD TRANSFERRED THE PRIMARY CONDUCTORS AND HAD REMOVED THE NEUTRAL FROM THE OLD POLE, LEAVING ONLY THE TELEPHONE LINE AND A TRANSFORMER ON THE OLD POLE. THE OLD POLE FELL INTO THE PRIMARY CONDUCTORS. THE OLD GUY, WHICH WAS STILL ATTACHED TO THE POLE AND TO ITS ANCHOR (ALONG WITH THE NEW GUY), CONTACTED ONE OF THE ENERGIZED PRIMARY CONDUCTORS. THE EMPLOYEE WHO WAS INSTALLING THE NEW GUY WAS HOLDING ONTO THE END OF THE NEW GUY. HE WAS ELECTROCUTED.

Keywords: OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, GUY, ELEC UTILITY WORK, UTILITY POLE

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 18054569 Fatality Electric Shock Electrical power installers and repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.