Inspection Detail
Inspection: 17878711 - Burke Scaffolding Co.
Inspection Information - Office: Manhattan Area Office
Site Address:
Burke Scaffolding Co.
Arthur Kill Generating Station Victory Blvd.
Staten Island, NY 07072
Mailing Address:
90 Commerce Road, Carlstadt, NJ 07072
Union Status: NonUnion
SIC:1799
NAICS: 0
Inspection Type: Unprog Rel
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 02/13/1991
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 03/01/1993
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 6 | 6 | ||||
Current Violations | 4 | 4 | ||||
Initial Penalty | $6,000 | $0 | $0 | $0 | $0 | $6,000 |
Current Penalty | $4,000 | $0 | $0 | $0 | $0 | $4,000 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260020 B01 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | J - ALJ Decision | |
2. | 01002 | Serious | 19260020 B02 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | J - ALJ Decision | |
3. | 01003 | Serious | 19260021 B02 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | R - Review Commission | Citation has been deleted. |
4. | 01004 | Serious | 19260451 A02 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | J - ALJ Decision | |
5. | 01005 | Serious | 19260451 A03 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | R - Review Commission | Citation has been deleted. |
6. | 01006 | Serious | 19260451 A15 | 03/21/1991 | 03/24/1991 | $1,000 | $1,000 | $0 | 04/11/1991 | J - ALJ Decision |
Investigation Summary
A KWIKSTAGE MODULAR FRAME SCAFFOLDING SYSTEM WAS ERECTED BY THE BURKE SCAFFOLDING COMPANY OF CARLSTADT, NEW JERSEY INSIDE BOILER #30 AT A CON EDISON OF NEW YORK POWER PLANT. THE SCAFFOLDING WAS COMPOSED OF 2 INCH METAL POLE UPRIGHTS FASTENED TO THE HORIZONTAL MEMBERS BY INSERTING FIXED WEDGES OF THE HORIZONTAL MEMBERS INTO THE "V" PRESSINGS ON THE UPRIGHTS. THESE INTERLOCKING COMPONENTS FORMED BAYS WHICH WERE ABOUT 8 FEET LONG, 6 FEET 6 INCHES HIGH AND 4 FEET AND 8 FEET IN WIDTH. THE SCAFFOLD, TIERED TO ABOUT 100 FEET, HAD A "DANCE FLOOR" ERECTED THEREON. FIVE ADDITIONAL 45 FOOT FREESTANDING TOWERS WERE ALSO ERECTED. EACH TOWER OF KWIKSTAGE SCAFFOLD WAS 8 FEET LONG, 6 FEET 6 INCHES HIGH AND 4 FEET WIDE AND HAD 11 TIERED BAYS. MORE THAN 9 EMPLOYEES WERE RENOVATING BOILER TUBING WHEN THE SCAFFOLD COLLAPSED. FIVE EMPLOYEES WERE HOSPITALIZED WITH INJURIES.
Keywords: COLLAPSE, CONSTRUCTION, FALL, SCAFFOLD
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 17878711 | Occupation Not Listed |