Powered by GoogleTranslate

Inspection Detail

Inspection: 17646712 - Edison Industrial Boiler Repair

Inspection Information - Office: Avenel Area Office

 

Inspection Nr: 17646712
Report ID: 0213400
Date Opened: 03/17/1987

Site Address:
Edison Industrial Boiler Repair
Baekeland Avenue
Middlesex, NJ 08846

Mailing Address:
85 Clipper Avenue, Edison, NJ 08817

Union Status: NonUnion

SIC:7699

NAICS: 0 


Inspection Type: Unprog Rel

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 03/30/1987

Emphasis:

Case Closed: 02/24/1988


Related Activity
Type Activity Nr Safety Health
Accident 360662639
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 2
Current Violations 2 2
Initial Penalty $220 $0 $0 $0 $0 $220
Current Penalty $220 $0 $0 $0 $0 $220
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 5A0001 05/08/1987 05/22/1987 $140 $140 $0 05/21/1987 F - Formal Settlement  
2. 01002 Serious 19260417 B 05/08/1987 05/22/1987 $80 $80 $0 05/21/1987 F - Formal Settlement  

Investigation Summary

Investigation Nr: 14308332
Event: 03/16/1987
EMPLOYEE KILLED IN BOILER EXPLOSION

THE REFRACTOR LINING OF A BOILER HAD BEEN REPAIRED. TO GAIN ACCESS TO THE BOILER, THE WIRING FOR THE BURNER CONTROLS HAD BEEN DISCONNECTED AND THE MAIN GAS VALVE SHUT OFF. AFTER THE REPAIRS WERE COMPLETED THE WIRING WAS RECONNECT BY A MECHANIC. THE MECHANIC HAD COMPILED AN INCOMPLETE LIST OF THE CONNECTIONS. THE MAIN GAS VALVE WAS THEN OPENED. EMPLOYEE #1 WAS CALLED TO START THE BOILER. HE CLOSED THE BREAKERS, BUT NOTHING HAPPENED. HE CHANGED A FUSE AND ATTEMPTED ANOTHER START-UP. EMPLOYEE #1, ALONG WITH 2 EMPLOYEES OF THE REPAIR COMPANY, WAS STANDING IN FRONT OF BURNER UNIT. AT THE POINT WHEN THE PILOT IS IGNITED, THE UNIT BLEW UP. A COVER PLATE ON THE BURNER UNIT BLEW OFF AND STRUCK EMPLOYEE #1 IN THE CHEST, KILLING HIM. THE BOILER WAS MANUFACTURED BY THE H.B. SMITH COMPANY, OF THE 28 SERIES, MODEL C3-GO-25. THE BURNER UNIT WAS MADE BY POWER FLAME, INC. THE DAY AFTER ACCIDENT, A TEST OF THE UNIT'S OPERATION WAS CONDUCTED AT THE REQUEST OF THE MIDDLESEX COUNTY PROSECUTORS OFFICE. WITH THE MAIN GAS VALVE CLOSED, THE BURNER WAS STARTED. IT WAS FOUND THAT THE GAS FEED VALVE TO THE BURNER WAS OPENING CONCURRENTLY WITH THE PURGE. NORMALLY THE FEED VALVE OPENS AFTER A 90 SECOND PURGE AND DETECTION OF THE PILOT FLAME. AN EXAMINATION OF THE WIRING SHOWED THAT THERE WAS A MISTAKE MADE WHEN THE WIRING WAS RECONNECTED, SUCH THAT THE SAFETY MEASURE (PURGE-FLAME DETECTION) HAD BEEN BYPASSED. PROPER START-UP PROCEDURES WERE NOT FOLLOWED. THE REWIRING JOB SHOULD HAVE BEEN CHECKED AGAINST THE WIRING DIAGRAM. A START-UP CHECK TO CHECK THE SAFETY MEASURE SHOULD HAVE BEEN DONE WITH THE MAIN GAS VALVE CLOSED.

Keywords: FLAMMABLE VAPORS, WORK RULES, BOILER, EXPLOSION, CHEST, STRUCK BY, FLYING OBJECT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 17646712 Occupation Not Listed
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.