Inspection Detail
Note: The following inspection has not been indicated as closed. OSHA citation items will be posted 30 (thirty) days after the employer receives the citation(s), except in cases of significant public interest. Posted citation items reflect any amendments to citations that are the result of a prompt settlement, which OSHA encourages. Employers and employee representatives will continue to receive copies of the citation(s) upon issuance.
Inspection: 1757420.015 - Jml Properties, Llc
Inspection Information - Office: Little Rock Area Office
Site Address:
Jml Properties, Llc
500 Napa Valley Dr
Little Rock, AR 72211
Mailing Address:
Po Box 1707, Muldrow, OK 74948
Union Status: NonUnion
SIC:
NAICS: 238110/Poured Concrete Foundation and Structure Contractors
Inspection Type: Fat/Cat
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Health
Close Conference: 06/25/2024
Emphasis: N:Heatnep
Case Closed:
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 2177972 | ||
Inspection | 1757968 | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 3 | 3 | ||||
Current Violations | 3 | 3 | ||||
Initial Penalty | $18,435 | $0 | $0 | $0 | $0 | $18,435 |
Current Penalty | $18,435 | $0 | $0 | $0 | $0 | $18,435 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 5A0001 | 12/19/2024 | 01/16/2025 | $6,452 | $6,452 | $0 | Z - Issued | ||
2. | 01002A | Serious | 19101200 E01 | 12/19/2024 | 01/16/2025 | $5,531 | $5,531 | $0 | Z - Issued | ||
3. | 01002B | Serious | 19101200 G08 | 12/19/2024 | 01/16/2025 | $0 | $0 | $0 | Z - Issued | ||
4. | 01003 | Serious | 19260021 B02 | 12/19/2024 | 01/16/2025 | $6,452 | $6,452 | $0 | Z - Issued |
Investigation Summary
On June 24, 2024, an employee working as a concrete finisher for a concrete contractor was busting 80-pound concrete bags into a pump machine. This work had been performed for approximately 2 to 4 hours. Around 2:44 p.m., the employee reported feeling disoriented and went to cool off inside a company truck. At approximately 3:05 p.m., the employee wandered away from where the work was being performed. At approximately 3:40 p.m., Coworker #1 and Coworker #2 found the employee unresponsive on the ground in front of a shipping container. The container was located approximately 200 feet from the truck. Coworker #2 poured bottles of water on the employee while Coworker #3 went to alert the Coworker #4, the foreman, who noticed Coworker #5, the General Manager via telephone. Coworker #5 told Coworker #4 to call 911. Coworker 3 called 911. The employee died from hyperthermia.
Keywords: Cardiovasc System, Concrete, Concrete Finisher, Concrete Pump, Construction, Dehydration, Heat, Heat Exhaustion, Heat Injury Prevention Program, Heat Stroke, Heat index, Heat-related illness , High Temperature, Hyperthermia , Lack of Work Procedures, Material Handling, Residential Construction, Respiratory Tract, Temperature
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1757420.015 | 33 | M | Fatality | Concrete and terrazzo finishers |