Note: The following inspection has not been indicated as closed. OSHA citation items will be posted 30 (thirty) days after the employer receives the citation(s), except in cases of significant public interest. Posted citation items reflect any amendments to citations that are the result of a prompt settlement, which OSHA encourages. Employers and employee representatives will continue to receive copies of the citation(s) upon issuance.

Inspection: 1749736.015 - Complete Power Pole Inspection Inc

Inspection Information - Office: Lubbock Area Office

 

Inspection Nr: 1749736.015
Report ID: 0627510
Date Opened: 05/21/2024

Site Address:
Complete Power Pole Inspection Inc
34.14379 N, 102.62150 W 2586 E. Highway 84
Muleshoe, TX 79347

Mailing Address:
P.O.Box 626, Littlefield, TX 79339

Union Status: NonUnion

SIC:

NAICS: 541990/ All Other Professional, Scientific, and Technical Services


Inspection Type: Fat/Cat

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 05/22/2024

Emphasis:

Case Closed:


Related Activity
Type Activity Nr Safety Health
Accident 2165395
Case Status: OPEN
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 3 3
Current Violations 3 3
Initial Penalty $14,517 $0 $0 $0 $0 $14,517
Current Penalty $7,259 $0 $0 $0 $0 $7,259
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100269 D02 I 09/26/2024 09/25/2025 $2,420 $4,839 $0 10/30/2024 F - Formal Settlement  
2. 01002 Serious 19100269 L03 III 09/26/2024 09/25/2025 $2,420 $4,839 $0 10/30/2024 F - Formal Settlement  
3. 01003 Serious 19100269 L04 II B 09/26/2024 09/25/2025 $2,420 $4,839 $0 10/30/2024 F - Formal Settlement  

Investigation Summary

Investigation Nr: 166774.015
Event: 05/20/2024
Employee dies from electrocution from electrical shock while

At 10:45 a.m. on May 20, 2024, a crew of four from Complete Power Pole Inspection, Inc., employed by the City of Lubbock, was preparing to reenergize power pole 0CR2 as part of their inspection and maintenance of powerlines running to water pumps. While being lifted in a bucket truck, Employee #1 came into contact with a live overhead power line, resulting in an electrical shock. The employee was immediately electrocuted and pronounced dead at the scene. The remaining three crew members were present at the scene but were not injured. Emergency medical services were called to the site, and the incident was reported to relevant authorities.

Keywords: Bucket Truck, Contact, Electric Shock, Electrocuted, Lift, Maintenance, Overhead Power Line, Water

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 1749736.015 48 M Fatality Electrical Power-Line
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.