Inspection Detail
Note: The following inspection has not been indicated as closed. OSHA citation items will be posted 30 (thirty) days after the employer receives the citation(s), except in cases of significant public interest. Posted citation items reflect any amendments to citations that are the result of a prompt settlement, which OSHA encourages. Employers and employee representatives will continue to receive copies of the citation(s) upon issuance.
Inspection: 1721955.015 - Jindal Tubular Usa Llc
Inspection Information - Office: Jackson Area Office
Site Address:
Jindal Tubular Usa Llc
13092 Seaplane Road
Bay Saint Louis, MS 39520
Mailing Address:
13092 Seaplane Road, Bay Saint Louis, MS 39520
Union Status: NonUnion
SIC:
NAICS: 331210/Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
Inspection Type: Fat/Cat
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 01/19/2024
Emphasis: N:Amputate, N:Dustexpl, L:Forklift
Case Closed:
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 2121711 | ||
Complaint | 2131475 | Yes | |
Inspection | 1752788 | Yes | |
Inspection | 1752796 | Yes | |
Inspection | 1730953 | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 13 | 3 | 16 | |||
Current Violations | 13 | 3 | 16 | |||
Initial Penalty | $197,497 | $0 | $338,765 | $0 | $0 | $536,262 |
Current Penalty | $197,497 | $0 | $191,160 | $0 | $0 | $388,657 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19100022 A01 | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
2. | 01001B | Serious | 19100022 A02 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
3. | 01002A | Serious | 19100037 B05 | 07/18/2024 | 08/30/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
4. | 01002B | Serious | 19100037 B02 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
5. | 01002C | Serious | 19100157 C01 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
6. | 01003 | Serious | 19100176 B | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
7. | 01004 | Serious | 19100176 G | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
8. | 01005A | Serious | 19100215 A04 | 07/18/2024 | 08/12/2024 | $12,676 | $12,676 | $0 | 08/06/2024 | J - ALJ Decision | |
9. | 01005B | Serious | 19100215 B09 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
10. | 01005C | Serious | 19100215 D01 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
11. | 01006 | Serious | 19100242 B | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
12. | 01007A | Serious | 19100303 B07 IV | 07/18/2024 | 08/12/2024 | $15,211 | $15,211 | $0 | 08/06/2024 | J - ALJ Decision | |
13. | 01007B | Serious | 19100303 C03 I | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
14. | 01008 | Serious | 19100303 B08 I | 07/18/2024 | 08/12/2024 | $15,211 | $15,211 | $0 | 08/06/2024 | J - ALJ Decision | |
15. | 01009 | Serious | 19100303 G01 I A | 07/18/2024 | 08/12/2024 | $10,140 | $10,140 | $0 | 08/06/2024 | J - ALJ Decision | |
16. | 01010 | Serious | 19100305 A02 V C | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
17. | 01011A | Serious | 19100305 D02 | 07/18/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | ||
18. | 01011B | Serious | 19100303 F02 | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
19. | 01012A | Serious | 19100305 G02 III | 07/18/2024 | 08/12/2024 | $15,211 | $15,211 | $0 | 08/06/2024 | J - ALJ Decision | |
20. | 01012B | Serious | 19100305 B01 II | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
21. | 01013A | Serious | 19100307 C | 07/18/2024 | 08/12/2024 | $16,131 | $16,131 | $0 | 08/06/2024 | J - ALJ Decision | |
22. | 01013B | Serious | 19100307 B | 07/18/2024 | 08/12/2024 | $0 | $0 | $0 | 08/06/2024 | J - ALJ Decision | |
23. | 02001 | Repeat | 19100022 A03 | 07/18/2024 | 08/12/2024 | $44,361 | $88,721 | $0 | 08/06/2024 | J - ALJ Decision | |
24. | 02002 | Repeat | 19100212 A01 | 07/18/2024 | 08/12/2024 | $102,439 | $161,323 | $0 | 08/06/2024 | J - ALJ Decision | |
25. | 02003 | Repeat | 19100335 A01 II | 07/18/2024 | 08/12/2024 | $44,361 | $88,721 | $0 | 08/06/2024 | J - ALJ Decision |
Investigation Summary
At 9:00 a.m. on January 19, 2024, two employees (Employee #1 and Employee #2) were setting up the site to create another stack of steel pipes (30 inches in diameter by 40 feet long, weighing over 2,000 pounds each.) The employees removed the chock block on the existing stack of pipes, causing the stack to collapse on top of both employees. Employee #1 was killed, and Employee #2 sustained multiple fractures to both legs and was hospitalized for treatment.
Keywords: Chock, Collapse, Falling Object, Fracture, Leg, Metal Pipe, Removal, Stack, Steel, Struck By
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1721955.015 | 20 | M | Hospitalized injury | Production helpers | |
2 | 1721955.015 | 25 | M | Fatality |