Inspection Detail
Inspection: 1689409.015 - City Of State Center
Inspection Information - Office: Iowa 0751910
Site Address:
City Of State Center
407 4th Avenue Ne
State Center, IA 50247
Mailing Address:
Po Box 668 118 E. Main Street, State Center, IA 50247
Union Status: NonUnion
SIC:
NAICS: 221122/Electric Power Distribution
Inspection Type: Fat/Cat
Scope: Partial
Advanced Notice: N
Ownership: LocalGovt
Safety/Health: Safety
Close Conference: 08/09/2023
Emphasis:
Case Closed: 02/07/2024
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 2064973 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 5 | 1 | 6 | |||
Current Violations | 3 | 1 | 4 | |||
Initial Penalty | $18,752 | $0 | $0 | $376 | $0 | $19,128 |
Current Penalty | $14,064 | $0 | $0 | $376 | $0 | $14,440 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19260097 C02 VIII | 11/27/2023 | 01/04/2024 | $4,688 | $4,688 | $0 | I - Informal Settlement | ||
2. | 01001B | Serious | 19260100 A | 11/27/2023 | 12/04/2023 | $0 | $0 | $0 | I - Informal Settlement | ||
3. | 01002A | Serious | 19260416 A01 | 11/27/2023 | 12/21/2023 | $0 | $4,688 | $0 | I - Informal Settlement | Citation has been deleted. | |
4. | 01002B | Serious | 19260416 A03 | 11/27/2023 | 12/21/2023 | $0 | $0 | $0 | I - Informal Settlement | Citation has been deleted. | |
5. | 01003A | Serious | 19260950 B01 I | 11/27/2023 | 01/04/2024 | $4,688 | $4,688 | $0 | I - Informal Settlement | ||
6. | 01003B | Serious | 19260950 B02 V | 11/27/2023 | 01/04/2024 | $0 | $0 | $0 | I - Informal Settlement | ||
7. | 01003C | Serious | 19260951 B01 | 11/27/2023 | 01/04/2024 | $0 | $0 | $0 | I - Informal Settlement | ||
8. | 01003D | Serious | 19260960 C01 III | 11/27/2023 | 01/04/2024 | $0 | $0 | $0 | I - Informal Settlement | ||
9. | 01004 | Serious | 19260957 B03 | 11/27/2023 | 01/04/2024 | $4,688 | $4,688 | $0 | I - Informal Settlement | ||
10. | 02001 | Other | 19040040 A | 11/27/2023 | 01/04/2024 | $376 | $376 | $0 | I - Informal Settlement |
Investigation Summary
At 8:00 a.m. on August 8, 2023, an employee was working to install a new transformer pad and basement in an alleyway. During the process of pulling conductors from the new switchgear through a conduit to the transformer, it was discovered the conduit was plugged. The employee walked down to the switchgear and opened the back of the cabinet. The employee was electrocuted and killed. The employee suffered burns.
Keywords: Basement, Conduit, Electric Conductor, Electrical Burn, Electrocuted, Installing, Switchgear, Transformer
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1689409.015 | 39 | M | Fatality | Supervisors; electricians & power transm. install. |