Inspection Detail
Inspection: 1615803.015 - Memphis Light Gas And Water - Electrical Distribution - Millington
Inspection Information - Office: Tenn Pub Sec 1
Site Address:
Memphis Light Gas And Water - Electrical Distribution - Millington
7407 Barrett Oaks Cove
Millington, TN 38053
Mailing Address:
Po Box 430, Memphis, TN 38103
Union Status: Union
SIC:
NAICS: 221122/Electric Power Distribution
Inspection Type: Fat/Cat
Scope: Partial
Advanced Notice: N
Ownership: LocalGovt
Safety/Health: Safety
Close Conference: 08/12/2022
Emphasis:
Case Closed: 11/16/2022
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 1936105 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 2 | ||||
Current Violations | 2 | 2 | ||||
Initial Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
Current Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260952 B | 10/17/2022 | 11/16/2022 | $0 | $0 | $0 | Z - Issued | ||
2. | 01002 | Serious | 19260961 C13 | 10/17/2022 | 11/16/2022 | $0 | $0 | $0 | Z - Issued |
Investigation Summary
At 1:30 p.m. on August 11, 2022, an employee was installing new electrical transformers at Memphis Light Gas and Water electric power distribution facility. A coworker closed the circuit before the employee completed his work. The employee was killed by electrocution.
Keywords:electric shock, electric current, electrical work, electrician, electrified, electrocuted, installing, maintenance, power plant, shock, transformer
# | Inspection | Age | Sex | Degree | Nature | Occupation |
---|---|---|---|---|---|---|
1 | 1615803.015 | Fatality | Electrical power installers and repairers |