Inspection Detail
Inspection: 1595142.015 - Wa317968607 - Base Square Llc
Inspection Information - Office: Dosh Tumwater Service Location, Tumwater, Wa
Site Address:
Wa317968607 - Base Square Llc
2606 Ne Horton Rd.
Woodland, WA 98674
Mailing Address:
1955 Se 182nd Ave, Portland, OR 97223
Union Status: NonUnion
SIC:
NAICS: 238390/Other Building Finishing Contractors
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Health
Close Conference: 06/23/2022
Emphasis:
Case Closed: 01/30/2023
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 1892011 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 7 | 2 | 9 | |||
Current Violations | 7 | 2 | 9 | |||
Initial Penalty | $22,500 | $0 | $0 | $0 | $0 | $22,500 |
Current Penalty | $700 | $0 | $0 | $0 | $0 | $700 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 296-155-270(6)(C) | 07/14/2022 | 04/08/2022 | $100 | $3,500 | $0 | 08/31/2022 | L - State Settlement | |
2. | 01002 | Serious | 296-155-280(1)(A) | 07/14/2022 | 04/08/2022 | $100 | $3,500 | $0 | 08/31/2022 | L - State Settlement | |
3. | 01003 | Serious | 296-155-456(2)(A) | 07/14/2022 | 04/08/2022 | $100 | $3,500 | $0 | 08/31/2022 | L - State Settlement | |
4. | 01004 | Serious | 296-155-260(3)(E) | 07/14/2022 | 01/06/2023 | $100 | $3,500 | $0 | 08/31/2022 | L - State Settlement | |
5. | 01005 | Serious | 296-901-14016(1) | 07/14/2022 | 01/06/2023 | $100 | $3,500 | $0 | 08/31/2022 | L - State Settlement | |
6. | 01006 | Serious | 296-901-14014(7) | 07/14/2022 | 12/27/2022 | $100 | $2,500 | $0 | 08/31/2022 | L - State Settlement | |
7. | 01007 | Serious | 296-155-100(1)(B) | 07/14/2022 | 08/01/2022 | $100 | $2,500 | $0 | 08/31/2022 | L - State Settlement | |
8. | 02001 | Other | 296-155-110(5)(A) | 07/14/2022 | 04/08/2022 | $0 | $0 | $0 | 08/31/2022 | L - State Settlement | |
9. | 02002 | Other | 296-27-031(1) | 07/14/2022 | 04/08/2022 | $0 | $0 | $0 | 08/31/2022 | L - State Settlement |
Investigation Summary
At 2:12 p.m. on April 1, 2022, an employee was applying flammable adhesive for flooring. An explosion and fire occured and killed the employee.
Keywords: Adhesive, Blunt force, Blunt force trauma, Burn, Chemical Vapor, Construction, Explosion, Fire, Flammable Vapors, Flooring , Installing, Lack of Engineering Controls, Vapor, Ventilation
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1595142.015 | 53 | M | Fatality | Occupation not reported |