Inspection Detail
Inspection: 1565852.015 - R&R Christo Construction, Llc
Inspection Information - Office: San Bernardino District Office
Site Address:
R&R Christo Construction, Llc
1455 N Warren Rd
San Jacinto, CA 92582
Mailing Address:
2200 Proctor Street, Fremont, NE 68025
Union Status: NonUnion
SIC:
NAICS: 321992/Prefabricated Wood Building Manufacturing
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 04/13/2022
Emphasis:
Case Closed: 06/30/2025
Type | Activity Nr | Safety | Health |
---|---|---|---|
Inspection | 1569063 | Yes | |
Accident | 1835593 | ||
Inspection | 1569058 | Yes | |
Inspection | 1569069 | Yes | |
Inspection | 1565898 | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 3 | 12 | 15 | |||
Current Violations | 3 | 12 | 15 | |||
Initial Penalty | $43,200 | $0 | $0 | $10,675 | $0 | $53,875 |
Current Penalty | $20,160 | $0 | $0 | $10,675 | $0 | $30,835 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Other | 1509(A) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
2. | 01002 | Other | 1509(B) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
3. | 01003 | Other | 1511(B) | 04/14/2022 | $1,050 | $1,050 | $0 | 05/05/2022 | L - State Settlement | ||
4. | 01004 | Other | 1512(B) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
5. | 01005 | Other | 1527(A) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
6. | 01006 | Other | 16710001 A01 | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
7. | 01007 | Other | 16710001 A | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
8. | 01008 | Other | 16710001 A06 | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
9. | 01009 | Other | 16710001 A | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
10. | 01010 | Other | 16710002 B | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
11. | 01011 | Other | 3205(C)(1) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
12. | 01012 | Other | 3395(I) | 04/14/2022 | $875 | $875 | $0 | 05/05/2022 | L - State Settlement | ||
13. | 02001 | Serious | 1621(A) | 04/14/2022 | $1,080 | $10,800 | $0 | 05/05/2022 | L - State Settlement | ||
14. | 03001 | Serious | 1626(C)(1) | 04/14/2022 | $1,080 | $10,800 | $0 | 05/05/2022 | L - State Settlement | ||
15. | 04001 | Serious | 17160002 E01 | 04/14/2022 | $18,000 | $21,600 | $0 | 05/05/2022 | L - State Settlement |
Investigation Summary
At 2:30 a.m. on November 16, 2021, an employee was applying mastic as part of a roof installation. At the top of the building where there was a 10 foot gap in the roof for ventilation purposes. The employee began walking backwards while applying mastic and fell through the gap to the ground 37 feet below. He fractured his femur in three places and was hospitalized.
Keywords: Fall, Fall From Elevation, Fracture, Leg, Roof, Roof Opening, Roofer, Thigh, Unguarded Fl Opening
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1565852.015 | 25 | M | Hospitalized injury | Construction laborers |