Inspection Detail

Case Status: CLOSED

Inspection: 1548904.015 - Massachusetts Electric Company

Inspection Information - Office: Springfield Area Office

 

Inspection Nr: 1548904.015
Report ID: 0112600
Date Opened: 08/20/2021

Site Address:
Massachusetts Electric Company
35 Willard St
Grafton, MA 01519

Mailing Address:
40 Sylvan Rd., Waltham, MA 02451

Union Status: NonUnion

SIC:

NAICS: 221118 


Inspection Type: Referral

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 11/19/2021

Emphasis:

Case Closed: 12/02/2022


Related Activity
Type Activity Nr Safety Health
Referral 1800951 Yes
Case Status: CLOSED
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 2
Current Violations 1 1
Initial Penalty $27,306 $0 $0 $0 $0 $27,306
Current Penalty $6,827 $0 $0 $0 $0 $6,827
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100269 A02 II 12/07/2021 01/19/2022 $0 $13,653 $0 I - Informal Settlement Citation has been deleted.
2. 01002 Serious 19100269 L05 I 12/07/2021 01/04/2022 $6,827 $13,653 $0 I - Informal Settlement  

Investigation Summary

Investigation Nr: 138342.015
Event: 08/20/2021
Employee sustains multiple injuries due to arc flash power l

At 9:30 a.m. on August 20, 2021, an employee working as a lineman for an electrical power generation company was part of a crew working on high voltage power lines. The crew was installing a low side cutout lead to the conductor on the road side phase. They were not aware of how to sufficiently cover the exposed live equipment with adequate lengths of protective line hoses and blankets prior to commencing with making low side connections. Additionally, the crew did not position themselves on the outside of the roadside line to minimize the arc flash potential posed by the center phase line. The employee was in the process of installing solid blades disconnects to tie two separate feeders together. The employee positioned himself between the center and road side phase in order to install a cut out when an arc flash occurred. The employee was hospitalized to treat chest, ear, and head injuries due to electrical shock, burns and the effects of the arc blast.

Keywords: Burn, Chest, Ear, Electric Arc, Electric Arc Flash, Electric Generator, Electric Shock, Electrical Wire, Electrical Work, Engineering Controls, Flash, Head, Hearing Loss, High Pressure, High Voltage, Installing, Lack of Engineering Controls, Overhead Power Line, PPE, PPE Hazard Assessment, Power Line Worker, Power Lines, Pressure, Pressure Release, Protective Clothing, Shock, Training

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 1548904.015 45 M Hospitalized injury Electrical Power-Line
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.