Inspection Detail
Note: The following inspection has not been indicated as closed. OSHA citation items will be posted 30 (thirty) days after the employer receives the citation(s), except in cases of significant public interest. Posted citation items reflect any amendments to citations that are the result of a prompt settlement, which OSHA encourages. Employers and employee representatives will continue to receive copies of the citation(s) upon issuance.
Inspection: 1496921.015 - Daniel Espinosa
Inspection Information - Office: Tennessee Osha Memphis Office - Safety
Site Address:
Daniel Espinosa
3940 Bobby Jones Rd
Memphis, TN 38125
Mailing Address:
5828 Lakeport Dr., Millington, TN 38053
Union Status: NonUnion
SIC:
NAICS: 238160/Roofing Contractors
Inspection Type: Fat/Cat
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 10/12/2020
Emphasis:
Case Closed:
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 1671344 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 2 | 5 | |||
| Current Violations | 3 | 2 | 5 | |||
| Initial Penalty | $8,600 | $0 | $0 | $1,200 | $0 | $9,800 |
| Current Penalty | $8,600 | $0 | $0 | $1,200 | $0 | $9,800 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260050 C | 01/22/2021 | 02/16/2021 | $600 | $600 | $0 | Z - Issued | ||
| 2. | 01002 | Serious | 19260416 A01 | 01/22/2021 | 02/16/2021 | $4,000 | $4,000 | $0 | Z - Issued | ||
| 3. | 01003 | Serious | 19260416 A03 | 01/22/2021 | 02/16/2021 | $4,000 | $4,000 | $0 | Z - Issued | ||
| 4. | 02001 | Other | TDLWD RULE 800-01-03-.05(1)(A)1 | 01/22/2021 | 02/16/2021 | $1,000 | $1,000 | $0 | Z - Issued | ||
| 5. | 02002 | Other | TDLWD RULE 800-01-03-.05(1)(A)2 | 01/22/2021 | 02/16/2021 | $200 | $200 | $0 | Z - Issued |
Investigation Summary
At 10:30 a.m. on September 8, 2020, Employees #1, #2, and #3, employed by a roofing company, were preparing to do re-roofing on a residential structure. They were setting up a platform hoist to lift shingles to the roof when they noticed the extension section on the hoist's base unit was installed backward. As they moved the hoist away from the roof to correct the extension section installation, the hoist made contact with overhead wires. The three employees sustained severe electric shock. Employee #1 was transported to a hospital emergency department, where he died from electrocution that afternoon. Employee #2 was transported to another hospital, where he died from electrocution on September 25, 2020. Employee #3 was transported to a hospital, admitted, treated for burns to his feet, and discharged four days later.
Keywords: Burn, Contact, Electric Shock, Electrocuted, Foot, Hoisting Mechanism, Material Handling, Overhead Power Line, Platform, Repair, Residential Construction, Roof, Roofer
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 1496921.015 | 27 | M | Fatality | Laborers, except construction | |
| 2 | 1496921.015 | 27 | M | Hospitalized injury | Roofers | |
| 3 | 1496921.015 | 42 | M | Fatality | Laborers, except construction |