Inspection Detail
Inspection: 1472495.015 - Pci Construction, Inc.
Inspection Information - Office: Dallas Area Office
Site Address:
Pci Construction, Inc.
University Place Phase 5
Richardson, TX 75080
Mailing Address:
405 Interchange St., Mc Kinney, TX 75071
Union Status: NonUnion
SIC:
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Referral
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 04/15/2020
Emphasis: N:Trench, L:Constr6
Case Closed: 12/19/2023
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Referral | 1571635 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 10 | 10 | ||||
| Current Violations | 3 | 5 | 8 | |||
| Initial Penalty | $121,450 | $0 | $0 | $0 | $0 | $121,450 |
| Current Penalty | $30,363 | $0 | $0 | $34,005 | $0 | $64,368 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19101200 H01 | 09/30/2020 | 05/16/2022 | $6,072 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 2. | 01002 | Other | 19260021 B02 | 09/30/2020 | 05/16/2022 | $6,073 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 3. | 01003 | Other | 19260050 B | 09/30/2020 | 05/16/2022 | $6,073 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 4. | 01004 | Serious | 19260651 G01 I | 09/30/2020 | 05/16/2022 | $12,145 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 5. | 01005 | Serious | 19260651 G02 I | 09/30/2020 | 10/13/2020 | $0 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | Citation has been deleted. |
| 6. | 01006 | Serious | 19260651 H01 | 09/30/2020 | 05/16/2022 | $6,073 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 7. | 01007 | Serious | 19260651 J01 | 09/30/2020 | 05/16/2022 | $12,145 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 8. | 01008 | Other | 19260651 K01 | 09/30/2020 | 05/16/2022 | $9,716 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | |
| 9. | 01009 | Serious | 19260652 A01 | 09/30/2020 | 10/13/2020 | $0 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement | Citation has been deleted. |
| 10. | 01010 | Other | 19261053 B01 | 09/30/2020 | 05/16/2022 | $6,072 | $12,145 | $0 | 10/20/2020 | F - Formal Settlement |
Investigation Summary
At approximately 3:15 P.M. on April 13, 2020, an employee, working for an excavation contractor, was building a new roadway. The employee was in a trench attempting to locate the sewer line when soil caved in. The employee was hospitalized and treated for an injury to the knee and fractured ribs.
Keywords: Caught In, Cave-In, Construction, Excavation, Fracture, Knee, Plumbing, Rib, Road, Sewer
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 1472495.015 | 27 | M | Hospitalized injury |