Inspection Detail
Note: The following inspection has not been indicated as closed. OSHA citation items will be posted 30 (thirty) days after the employer receives the citation(s), except in cases of significant public interest. Posted citation items reflect any amendments to citations that are the result of a prompt settlement, which OSHA encourages. Employers and employee representatives will continue to receive copies of the citation(s) upon issuance.
Inspection: 1405952.015 - Green Smile Energy And Electric Age And Dia Teck
Inspection Information - Office: Santa Ana District Office
Site Address:
Green Smile Energy And Electric Age And Dia Teck
2011 W Raymer Ave
Fullerton, CA 92835
Mailing Address:
1755 Leaning Pine Dr, Diamond Bar, CA 91765
Union Status: NonUnion
SIC:
NAICS: 238210/Electrical Contractors
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 11/15/2019
Emphasis:
Case Closed:
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 1462364 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 3 | 5 | |||
Current Violations | 2 | 2 | 4 | |||
Initial Penalty | $32,400 | $0 | $0 | $6,120 | $0 | $38,520 |
Current Penalty | $11,360 | $0 | $0 | $1,120 | $0 | $12,480 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Other | 342(A) | 11/15/2019 | 12/20/2019 | $0 | $5,000 | $0 | 01/14/2020 | O - Administrative Law Judge Order | Citation has been deleted. |
2. | 01002 | Other | 3203(A) | 11/15/2019 | 12/20/2019 | $560 | $560 | $0 | 01/14/2020 | O - Administrative Law Judge Order | |
3. | 01003 | Other | 3395(I) | 11/15/2019 | 12/20/2019 | $560 | $560 | $0 | 01/14/2020 | O - Administrative Law Judge Order | |
4. | 02001 | Serious | 23200002 A | 11/15/2019 | 11/27/2019 | $10,800 | $16,200 | $0 | 01/14/2020 | O - Administrative Law Judge Order | |
5. | 03001 | Serious | 23200011 A01 | 11/15/2019 | 11/27/2019 | $560 | $16,200 | $0 | 01/14/2020 | O - Administrative Law Judge Order |
Investigation Summary
At 10:01 a.m. on May 31, 2019, Employees #1, #2, and #3, employed by an electrical contractor, were dismantling and removing electrically powered yard dying equipment from a closing factory. To remove large gauge copper electrical wiring from an electrical panel, Employee #1, the supervisor, used a hand-held battery powered grinder with a cutting wheel installed. The covers had been removed and the power had not been disconnected/secured. During the cutting, live electrical wires containing different phases of power came into contact with each other and created a phased electrical arc flash and explosion. The employees were transported to the hospital for treatment of electrical burns. Employee #1, who received the bulk of the arc flash, was hospitalized for treatment of severe burns to his upper body and arms. Employees #2 and #3 sustained minor to moderate burn injuries. They were treated and released without hospitalization.
Keywords: Arm, Construction, Contact, Cutting, Demolition, Dismantling, Electric Arc Flash, Electrical Burn, Electrical panel, Explosion, Grinder, Lockout/Tagout, Torso, Unsecured Panel
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 1405952.015 | 61 | M | Non Hospitalized injury | Laborers, except construction | |
2 | 1405952.015 | 99 | M | Non Hospitalized injury | Laborers, except construction | |
3 | 1405952.015 | 57 | M | Hospitalized injury | Electrical and electronic engineers |