Inspection Detail
Inspection: 1360326.015 - Paragon Construction And Development Inc.
Inspection Information - Office: Mobile Area Office
Site Address:
Paragon Construction And Development Inc.
Sapphire Dialysis 8149 Decker Lane
Montgomery, AL 36117
Mailing Address:
P. O. Box 241424, Montgomery, AL 36124
Union Status: NonUnion
SIC:
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Fat/Cat
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 11/15/2018
Emphasis: L:Fall
Case Closed: 08/04/2020
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 1407377 | ||
| Inspection | 1360313 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 1 | 1 | 2 | |||
| Initial Penalty | $24,508 | $0 | $0 | $0 | $0 | $24,508 |
| Current Penalty | $10,608 | $0 | $0 | $0 | $0 | $10,608 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260501 A02 | 04/29/2019 | 05/07/2019 | $10,608 | $13,260 | $0 | 05/22/2019 | J - ALJ Decision | |
| 2. | 01002 | Other | 19260503 A01 | 04/29/2019 | 05/07/2019 | $0 | $11,248 | $0 | 05/22/2019 | J - ALJ Decision |
Investigation Summary
At 9:30 a.m. on November 13, 2018, an employee was installing rolled bat insulation in the attic area. The employee fell through the rafter area and dropped down from the acoustical ceiling on to the concrete floor. The employee was initially hospitalized and then later died.
Keywords: Fall, Installing, Rafter
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 1360326.015 | 65 | M | Fatality | Construction laborers |
Translate