Inspection Detail
Note: The following inspection has not been indicated as closed. Please be aware that the information shown may change, e.g. violations may be added or deleted. For open cases, in which a citation has been issued, the citation information may not be available for 5 days following receipt by the employer for Federal inspections or for 30 days following receipt by the employer for State inspections.
Inspection: 1320857.015 - R. F. Warder, Inc.
Inspection Information - Office: Maryland Region 3
Site Address:
R. F. Warder, Inc.
2100 Block Of Sinclair Lane Near N. Chester Street
Baltimore, MD 21213
Mailing Address:
10556 Philadelphia Road, White Marsh, MD 21162
Union Status: Union
SIC:
NAICS: 238220/ Plumbing, Heating, and Air-Conditioning Contractors
Inspection Type: Fat/Cat
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 09/11/2018
Emphasis: N:Trench, S:Crshstrk
Case Closed:
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 1345323 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 4 | 2 | 8 | ||
Current Violations | 1 | 4 | 2 | 7 | ||
Initial Penalty | $1,950 | $274,500 | $0 | $600 | $0 | $277,050 |
Current Penalty | $900 | $274,500 | $0 | $600 | $0 | $276,000 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260100 A | 11/19/2018 | 11/29/2018 | $900 | $900 | $0 | 12/11/2018 | R - Review Commission | |
2. | 01002 | Serious | 19260651 C02 | 11/19/2018 | 11/29/2018 | $1,050 | $1,050 | $0 | 12/11/2018 | R - Review Commission | Citation has been deleted. |
3. | 02001 | Willful | 19260021 B02 | 11/19/2018 | 12/26/2018 | $122,000 | $122,000 | $0 | 12/11/2018 | R - Review Commission | |
4. | 02002 | Willful | 19260651 H01 | 11/19/2018 | 11/29/2018 | $30,500 | $30,500 | $0 | 12/11/2018 | R - Review Commission | |
5. | 02003 | Willful | 19260651 K01 | 11/19/2018 | 11/29/2018 | $30,500 | $30,500 | $0 | 12/11/2018 | R - Review Commission | |
6. | 02004 | Willful | 19260652 A01 | 11/19/2018 | 11/29/2018 | $91,500 | $91,500 | $0 | 12/11/2018 | R - Review Commission | |
7. | 03001 | Other | 5-503(A) | 11/19/2018 | 12/26/2018 | $300 | $300 | $0 | 12/11/2018 | R - Review Commission | |
8. | 03002 | Other | 05-503(C)(1)(I) | 11/19/2018 | 12/26/2018 | $300 | $300 | $0 | 12/11/2018 | R - Review Commission |
Investigation Summary
At 3:30 p.m. on June 5, 2018, an employee was using a high pressure hose to clea n a storm drain that was inside a trench. During work, the trench collapsed, bur ying the employee in approximately 15 feet of dirt and debris. The employee was killed.
Keywords:buried, collapse, trench
# | Inspection | Age | Sex | Degree | Nature | Occupation |
---|---|---|---|---|---|---|
1 | 1320857.015 | Fatality | Laborers, except construction |