Inspection: 126156751 - Ppr A Repipe Company

Inspection Information - Office: Los Angeles District Office

 

Inspection Nr: 126156751
Report ID: 0950641
Date Opened: 03/26/2003

Site Address:
Ppr A Repipe Company
2011 Main Street
Santa Monica, CA 90405

Mailing Address:
6910 Mission Gorge Road, San Diego, CA 92120

Union Status: NonUnion

SIC:1711

NAICS: 238220/ Plumbing, Heating, and Air-Conditioning Contractors


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 03/26/2003

Planning Guide: Safety-Construction

Emphasis: S:Construction (Cship)

Case Closed: 09/23/2003


Related Activity
Type Activity Nr Safety Health
Accident 362579757
Accident 362584674
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 1 4 5
Current Violations 1 4 5
Initial Penalty $2,475 $0 $0 $1,855 $0 $4,330
Current Penalty $550 $0 $0 $1,305 $0 $1,855
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Other 5157 E02 09/19/2003 10/22/2003 $550 $550 $0 04/20/2004 W - Empr Withdrew  
2. 01002 Other 5157 F 09/19/2003 10/22/2003 $0 $550 $0 04/20/2004 W - Empr Withdrew  
3. 01003 Other 5157 D04 D 09/19/2003 10/22/2003 $550 $550 $0 04/20/2004 W - Empr Withdrew  
4. 01004 Other 1670 B19 09/19/2003 10/22/2003 $205 $205 $0 04/20/2004 F - Formal Settlement  
5. 02001 Serious 5157 C05 B2 09/19/2003 10/22/2003 $550 $2,475 $0 04/20/2004 W - Empr Withdrew  

Investigation Summary

Investigation Nr: 201164837
Event: 03/26/2003
Employee overcome by fumes in sewer pipe

Employee #1 and six other employees were relining a 30-inch sewer pipe with a Rotoloc Machine. Rotoloc, a system which relines exiting pipelines, is designed so that new pipe walls are rotated into the system using the existing pipe as a host for the new material. The employees were working on sewer manholes identified as MH 33-2-2-25 and MH 33-2-2-32. The two manholes were connected with a 30-inch sewer pipeline approximately 404 feet long. After the initial air monitoring, two employees entered each of the manholes. Employee #1 and another employee entered the upstream manhole and two other employees entered the downstream manhole. Employee #1 crawled approximately 75 to 100 feet into the 30-inch sewer line while the other employee entered at approximately 150 feet to operate the Rotoloc Machine. Immediately after their entry, a noxious odor became prevalent due to a discharge from the lateral line. The discharge may have occurred from a furniture re-finishing establishment located on the street above. The attendants signaled both employees to evacuate the space. During the evacuation, Employee #1 was overcome by the fumes and became unconscious. Employees working in the down stream manhole exited the space safely. Employee #1 was extracted and revived by fellow employees and was transported to a UCLA Medical Center for treatment of chemical burns on his back.

Keywords: BURN, SEWER, UNCONSCIOUSNESS, BACK, CHEMICAL

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 126156751 Non Hospitalized injury Burn(Chemical) Construction laborers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.