Inspection Detail
Inspection: 122191091 - Prairie Central Maintenance & Fabrication
Inspection Information - Office: Peoria Area Office
Site Address:
Prairie Central Maintenance & Fabrication
Adm Cogen Plant, 4666 Faries Pkwy
Decatur, IL 62526
Mailing Address:
3536 N.27th St., P.O. Box 3007, Decatur, IL 62524
Union Status: NonUnion
SIC:7349
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Health
Close Conference: 05/21/1996
Emphasis:
Case Closed: 11/07/1997
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 360358360 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 3 | 1 | 4 | |||
Current Violations | 3 | 1 | 4 | |||
Initial Penalty | $8,550 | $63,000 | $0 | $0 | $0 | $71,550 |
Current Penalty | $4,275 | $0 | $0 | $0 | $50,400 | $54,675 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19100132 A | 06/06/1996 | 06/18/1996 | $1,575 | $3,150 | $0 | 06/25/1996 | F - Formal Settlement | |
2. | 01001B | Serious | 19100132 D01 | 06/06/1996 | 06/18/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
3. | 01001C | Serious | 19100132 D02 | 06/06/1996 | 06/18/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
4. | 01001D | Serious | 19100132 F01 | 06/06/1996 | 06/25/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
5. | 01001E | Serious | 19100132 F04 | 06/06/1996 | 06/25/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
6. | 01002A | Serious | 19100269 D02 III | 06/06/1996 | 07/24/1996 | $1,125 | $2,250 | $0 | 06/25/1996 | F - Formal Settlement | |
7. | 01002B | Serious | 19100269 D02 V | 06/06/1996 | 07/24/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
8. | 01002C | Serious | 19100269 D02 VI | 06/06/1996 | 07/25/1996 | $0 | $0 | $0 | 06/25/1996 | F - Formal Settlement | |
9. | 01003 | Serious | 19101200 H | 06/06/1996 | 06/25/1996 | $1,575 | $3,150 | $0 | 06/25/1996 | F - Formal Settlement | |
10. | 02001 | Unclass | 19100269 D02 III | 06/06/1996 | 07/24/1996 | $50,400 | $63,000 | $0 | 06/25/1996 | F - Formal Settlement |
Investigation Summary
Employee #1 had been hired by PCM about three weeks ago through Temporary Services of Decatur. Employee #2 is a permanent PCM employee with approximately six months service. They were assigned to replace the "socks" in module #7 of the baghouse for boiler #4, at the Archer Daniels Midland (ADM) co-gen plant, Decatur, IL. A water pipe inside boiler #4 ruptured, and the water was instantly turned to steam by the exhaust flue temperature. Steam traveled through the dust collection system and burst into the baghouse. Employee #2 escaped with second-degree burns on his face, forearms, waist, and legs. Employee #1 did not make it out of the baghouse and was killed.
Keywords: BURN, DUST COLLECTOR, EQUIPMENT FAILURE, RUPTURE, STEAM, PIPE, FACE, HIGH TEMPERATURE
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 122191091 | Hospitalized injury | Burn/Scald(Heat) | Occupation not reported | ||
2 | 122191091 | Fatality | Burn/Scald(Heat) | Occupation not reported |