Inspection: 116240433 - Ajax Pipe Line Company
Inspection Information - Office: Charleston Area Office
Site Address:
Ajax Pipe Line Company
2043 Wilson Street
Dunbar, WV 25064
Mailing Address:
Po Box 6190, Charleston, WV 25362
Union Status: NonUnion
SIC:1311
NAICS: 0
Inspection Type: Accident
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 10/17/1994
Emphasis:
Case Closed: 04/20/1995
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 361891633 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 6 | 2 | 8 | |||
Current Violations | 6 | 2 | 8 | |||
Initial Penalty | $4,650 | $0 | $0 | $1,800 | $0 | $6,450 |
Current Penalty | $2,550 | $0 | $0 | $300 | $0 | $2,850 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001A | Serious | 19260059 E01 | 11/01/1994 | 11/24/1994 | $450 | $450 | $0 | - | ||
2. | 01001B | Serious | 19260059 G08 | 11/01/1994 | 11/24/1994 | $0 | $0 | $0 | - | ||
3. | 01001C | Serious | 19260059 H | 11/01/1994 | 11/24/1994 | $0 | $0 | $0 | - | ||
4. | 01002 | Serious | 19260602 A02 I | 11/01/1994 | 11/29/1994 | $750 | $750 | $0 | - | ||
5. | 01003 | Serious | 19260404 F07 IVC1 | 11/01/1994 | 11/09/1994 | $0 | $600 | $0 | I - Informal Settlement | ||
6. | 01004 | Serious | 19260021 B02 | 11/01/1994 | 11/09/1994 | $0 | $750 | $0 | I - Informal Settlement | ||
7. | 01005 | Serious | 19260652 C01 | 11/01/1994 | 11/09/1994 | $750 | $1,500 | $0 | I - Informal Settlement | ||
8. | 01006 | Serious | 19260404 B01 I | 11/01/1994 | 11/09/1994 | $600 | $600 | $0 | - | ||
9. | 02001 | Other | 19040008 A | 11/01/1994 | 11/09/1994 | $0 | $1,500 | $0 | I - Informal Settlement | ||
10. | 02002 | Other | 19030002 A01 | 11/01/1994 | 11/09/1994 | $300 | $300 | $0 | - |
Investigation Summary
Employees #1 through #3 were installing a new gas line. Gas in the line ignited, and Employees #1, #2 and #3 were burned. They required hospitalization.
Keywords: BURN, FUEL LINE, INSTALLING, GAS WELL, WORK RULES, GAS, GAS WELL DRILLING
# | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
---|---|---|---|---|---|---|
1 | 116240433 | Hospitalized injury | Burn/Scald(Heat) | Occupation not reported | ||
2 | 116240433 | Hospitalized injury | Burn/Scald(Heat) | Occupation not reported | ||
3 | 116240433 | Hospitalized injury | Burn/Scald(Heat) | Occupation not reported |