Inspection Detail
Inspection: 1134967.015 - Jacksonville Marine Construction, Inc.
Inspection Information - Office: Jacksonville Area Office
Site Address:
Jacksonville Marine Construction, Inc.
8720 Mckenna Dr
Jacksonville, FL 32226
Mailing Address:
10945 Patton Road, Jacksonville, FL 32246
Union Status: NonUnion
SIC:
NAICS: 237990/Other Heavy and Civil Engineering Construction
Inspection Type: Fat/Cat
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 05/25/2016
Emphasis: L:Fall
Case Closed: 02/17/2021
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 1074172 | ||
| Referral | 1101525 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 10 | 3 | 13 | |||
| Current Violations | 9 | 2 | 11 | |||
| Initial Penalty | $66,100 | $0 | $0 | $4,200 | $0 | $70,300 |
| Current Penalty | $35,150 | $0 | $0 | $700 | $0 | $35,850 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260605 B02 | 08/30/2016 | $4,000 | $4,988 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 2. | 01002A | Serious | 19261412 D01 | 08/30/2016 | $3,650 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 3. | 01002B | Serious | 19261412 E03 I A | 08/30/2016 | $0 | $0 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 4. | 01002C | Serious | 19261412 F01 | 08/30/2016 | $0 | $0 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 5. | 01003 | Serious | 19261415 A02 | 08/30/2016 | $4,500 | $8,730 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 6. | 01004 | Serious | 19261417 O01 | 08/30/2016 | $4,500 | $8,730 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 7. | 01005 | Serious | 19261424 A02 II | 08/30/2016 | $3,700 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 8. | 01006 | Serious | 19261427 F01 | 08/30/2016 | 09/12/2016 | $0 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | Citation has been deleted. |
| 9. | 01007 | Serious | 19261428 A | 08/30/2016 | 01/30/2018 | $3,700 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | |
| 10. | 01008 | Serious | 19261437 E01 | 08/30/2016 | $3,700 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 11. | 01009 | Serious | 19261437 E03 | 08/30/2016 | $3,700 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | ||
| 12. | 01010A | Serious | 19261437 H01 | 08/30/2016 | 01/30/2018 | $3,700 | $6,236 | $0 | 09/22/2016 | F - Formal Settlement | |
| 13. | 01010B | Serious | 19261437 H02 | 08/30/2016 | 01/30/2018 | $0 | $0 | $0 | 09/22/2016 | F - Formal Settlement | |
| 14. | 01010C | Serious | 19261437 H04 | 08/30/2016 | 01/30/2018 | $0 | $0 | $0 | 09/22/2016 | F - Formal Settlement | |
| 15. | 02001 | Other | 19040004 A | 08/30/2016 | 01/30/2018 | $700 | $700 | $0 | 09/22/2016 | F - Formal Settlement | |
| 16. | 02002 | Other | 19040039 A01 | 08/30/2016 | $0 | $3,500 | $0 | 09/22/2016 | F - Formal Settlement | Citation has been deleted. | |
| 17. | 02003 | Other | 19261433 D03 | 08/30/2016 | 01/30/2018 | $0 | $0 | $0 | 09/22/2016 | F - Formal Settlement |
Investigation Summary
At approximately 3:00 p.m. on March 5, 2016, an employee was unhooking a load by removing the sling from the wood piling. As the employee released the sling from the load, the hook swung a few feet and struck his hard hat. The employee received head injuries and was killed.
Keywords: Head, Sling, Struck By
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 1134967.015 | 31 | M | Fatality | Construction laborers |
Translate