Inspection Detail
Inspection: 112535760 - New River Electrical Corporation
Inspection Information - Office: Columbus Area Office
Site Address:
New River Electrical Corporation
29710 Hoover-Moffitt Rd. (Cr 310)
Raymond, OH 43067
Mailing Address:
P.O. Box 70, Cloverdale, VA 24077
Union Status: NonUnion
SIC:1623
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 04/20/2001
Emphasis: S:Construction Fatalities
Case Closed: 01/24/2002
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 100751049 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 3 | ||||
| Current Violations | 1 | 1 | ||||
| Initial Penalty | $15,350 | $0 | $0 | $0 | $0 | $15,350 |
| Current Penalty | $3,000 | $0 | $0 | $0 | $0 | $3,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260021 B02 | 05/21/2001 | 06/23/2001 | $7,000 | $7,000 | $0 | 05/31/2001 | F - Formal Settlement | Citation has been deleted. |
| 2. | 01002 | Serious | 19260453 B02 V | 05/21/2001 | 06/23/2001 | $3,000 | $1,350 | $0 | 05/31/2001 | F - Formal Settlement | |
| 3. | 01003 | Serious | 19260950 C02 I | 05/21/2001 | 06/08/2001 | $7,000 | $7,000 | $0 | 05/31/2001 | F - Formal Settlement | Citation has been deleted. |
Investigation Summary
A power line crew was replacing a utility pole on an existing 12-kilovolt, three-phase overhead power line. The employees had set the new 15.2-meter pole about 2 meters from the existing 13.7-meter pole. The power line conductors were positioned on hot arms attached to the crossarm on the new pole. A step-seven apprentice power line worker on the crew was working from an aerial lift. As he was using a handline to pull a guy up to install it on the pole, he contacted the center phase conductor with the back of his neck and upper back and received an electric shock. He died of his injuries 2 days after the accident.
Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, ELEC UTILITY WORK, AERIAL LIFT
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 112535760 | Fatality | Electric Shock | Electrical power installers and repairers |